Question 1 In the project below, the time duration and symbol of each activity are given. Identify the critical path (Without
Correct using CPM; hint: identify all possible paths and find their lengths)?
Mark 1.00 out of
1.00
a. A B E H
b. A C D H
c. A B D H
d. A F G H
The correct answer is:
A B D H
Question 2 In the project below, the time duration and symbol of each activity are given. Compute the duration of the
,Correct longest path in the project (without using CPM; hint: identify all possible paths and find their lengths)?
Mark 1.00 out of
1.00
a. 17
b. A B E H
c. 21
d. 20
The correct answer is:
21
Question 3 In the project below, the time duration and symbol of each activity are given. What's the slack of path A- C-D-H ?
Correct
Mark 1.00 out of
1.00
, a. A B E H
b. 17
c. 3
d. 4
The correct answer is:
3
Question 4
In the project below, the time duration and symbol of each activity are given. Compute how long should the project take
Correct
Mark 1.00 out of
1.00
from start to finish using the CPM method?
a. 11
b. 12
c. 18
d. 21
The correct answer is:
18
, Question 5 In the project below, the time duration and symbol of each activity are given. Compute the early start of activity 'E'
Correct using the CPM method?