CAPM Practice Exam 150 Questions & Answers 2023/2024. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called Management by objectives During the full life cycle of the project, a plot of the project's expected expenditures will usually follow a characteristic S curve. This indicates that the bulk of the project budget will be spent in the execution phase n which project lifecycle phase would you expect to have the greatest influence on overall project cost? concept Requirement is Quantified and documented needs of stakeholders Quantified and documented expectations of customer Quantified and documented expectations of sponsor (all the above) TQM is Total Quality Management A common approach to implementing a quality improvement program Of the following, which describes Management Information Systems? Software that an enterprise uses to support business and administrative operations The type of planning that is equated with more specific data or is detailed in nature is called tactical What are the different types of costs in Microsoft Project? Fixed Cost, Cost Per Use, Standard Cost, Overtime Cost What is the name of PMI's Organization maturity model for project management? OPM3

Mostrar más Leer menos
Institución
Grado









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Grado

Información del documento

Subido en
7 de octubre de 2023
Número de páginas
11
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CAPM Practice Exam 150 Questions & Answers
2023/2024.
The process of establishing clear and achievable objectives, measuring their
achievement, and adjusting performance in accordance with the results of the
measurement is called
Management by objectives
During the full life cycle of the project, a plot of the project's expected
expenditures will usually follow a characteristic S curve. This indicates that
the bulk of the project budget will be spent in the execution phase
n which project lifecycle phase would you expect to have the greatest influence
on overall project cost?
concept
Requirement is
Quantified and documented needs of stakeholders
Quantified and documented expectations of customer
Quantified and documented expectations of sponsor
(all the above)
TQM is
Total Quality Management
A common approach to implementing a quality improvement program
Of the following, which describes Management Information Systems?
Software that an enterprise uses to support business and administrative operations
The type of planning that is equated with more specific data or is detailed in
nature is called
tactical
What are the different types of costs in Microsoft Project?
Fixed Cost, Cost Per Use, Standard Cost, Overtime Cost
What is the name of PMI's Organization maturity model for project management?
OPM3
Which of the following is NOT a characteristic of a Project?
It is managed in strict accordance with the PMBOK guidelines
A group of related projects that are managed in a coordinated way that usually
includes an element of ongoing activity is called a:
Program
Project constraint could be on
cost
resources
schedule
(all of the above)
Which of the following is NOT true about Project Management Office (PMO)?
PMO is not involved in coordinating communication across projects
Projects require project management while operations require business process
management or operations management. Projects can intersect with operations

, at various points during the product lifecycle. Which of the following is not a
stage to represent this?
At each executing phase
Enterprise environmental factors refer to both internal and external
environmental factor that surround or influence a project's success. Of the
following, which is NOT an enterprise environmental factor
historical data
A person who is involved in or may be affected by the activities or anyone who
has something to gain or lose by the activity of the project is called a:
stakeholder
Large projects may be divided into smaller, more manageable components
known as,
subprojects
A manager who manages a group of related projects is called a -
Program manager
Which of the following activity is conducted last as part of closing process group
customer satisfaction survey
In the PMBOK, each process is broken into -
Inputs and Outputs
Tools and techniques
A stakeholder has the greatest ability to influence a project during -
Initiation and Planning
A Project Manager should support making changes during Execution -
When they are warranted and inline with the strategic goals of the organization
Conducting Lessons Learned is a critical part of -
Closing
Of the following, which is not a process from the Planning Process Group?
Perform Quality Assurance
The Change Management Plan should be included in which of the following?
Project Management Plan
Who is a Project Initiator?
A person or organization that has the ability and authority to start the project
Who does the Project Integration?
Project Manager
Which of the following is true about Project Plan ?
Project Plan needs to have the buy in of the entire project team
Which of the following statements is MOST True?
The project charter names and authorizes the project manager
Which of the following may NOT be included in the Project Management Plan?
Performance measurement report
All of the following are TRUE except,
Any and all changes to the approved project management plan should be
discouraged
The project is characterized by frequent changes to the project charter.
Authorizing project charter changes should typically be the responsibility of
Senior management
$10.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
LectDan Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
213
Miembro desde
3 año
Número de seguidores
157
Documentos
7578
Última venta
1 mes hace

4.1

46 reseñas

5
25
4
12
3
1
2
3
1
5

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes