ENG 101 Mod 3 Tests LATEST UPDATE 1) Key output(s) of the Technical Planning Process include: Select the two
correct answers. [Describe the purpose, inputs and outputs, and activities of the Technical
Planning Process.] [Remediation Accessed :N]
Applicable policies, procedures, and
processes
Any previously developed technical
plans
A Test and Evaluation Master Plan
(TEMP)
A Systems Engineering Plan
(SEP)
2) A technical management plan which helps to "ensure that the various
elements of the system are functionally, physically, and electronically
capable of interacting with each other and with all external links" , is the:
[Identify typical technical management plans.]
Interface Management
Plan.
Risk Management
Plan.
Software Development
Plan.
Logistics Support
Plan.
Test and Evaluation Master
Plan.
3) All the following are examples of so-called "specialty technical plans",
EXCEPT for: [Identify specialty engineering technical management plans.]
Acquisition
Strategy.
Security
Plan.
Programmatic, Environment, Safety, and Occupational Health
(PESHE) Plan.
Producibility
Plan.
Reliability
Plan.
4) Systems Engineering Plan should cover: Select the four correct answers.
[Describe the contents of a Systems Engineering Plan (SEP).]
Systems Engineering
Processes
Enabling facilities for Systems
Engineering
Systems Engineering event
timing
Validation and verification test
scenarios
Enabling Systems Engineering
tools
5) Event-based planning is orchestrated mainly around: Select the two
correct answers. [Explain the difference between event-based and calendar-based
scheduling.] [Remediation Accessed :N]
Technical events and associated
tasks.
Network charts linking task and events by
time.
Time duration and calendar
dates.
Task Entry and Exit criteria.
1) Key input(s) to the Technical Planning Process include: Select the
three correct answers. [Describe the purpose, inputs and outputs, and activities of the
Technical Planning Process.]
A Systems Engineering Plan (SEP) and other
plans.
Regulatory
requirements
Defense acquisition lifecycle phase
requirements.
Any previously developed technical
plans.
A Test and Evaluation Master Plan
(TEMP).
2) Calendar-based planning is orchestrated mainly around: Select the two
correct answers. [Explain the difference between event-based and calendar-based
scheduling.] [Remediation Accessed :N]
Calendar dates of each event
initiation.
Knowledge of task completion
criteria.
Technical events and associated
tasks.
Network charts linking task and events by time
1) In general, the preferable approach to scheduling is to develop a
schedule from an event-based perspective, but then convert it to a
calendar-based schedule using engineering judgment based on the
duration estimate to achieve the event-based criteria. [Explain the difference
between event-based and calendar-based scheduling.]
Fals
e
True
1) The purpose of the Requirements Management Process is to maintain
traceability of all requirements from their origins; to document changes to
them and to record the rationale for requirements changes. [Describe the
purpose, inputs and outputs, and activities of the Requirements Management Process.]
True
Fals
e
2) "Traceability", from the perspective of the Requirements Management
Process, encompasses two bi-directional aspects: (1) traceability up to the
Systems Specification and capability; and (2) traceability down to the
lowest-level end product. [Explain why maintaining traceability between requirements is
important.]
Fals
e
True
1) Key output(s) of the Interface Management Process include: Select the
two correct answers. [Describe the purpose, inputs and outputs, and activities of the
Interface Management Process.]
An Interface Management
Plan.
Interface
Requirements.
Interface Control
Documents.
Interface
Specifications.
2) The DoD defines an "Open Systems" interface as one having which of
the following attributes? Select the two correct answers. [Identify different
types of interface.]
Using widely supported, consensus-based
standards.
Implement via secure, military
standards.
Implemented via secure, proprietary
standards.
Based around a modular
design.
3) An internal interface can be defined as: "those boundaries between
products within a system model that are controlled by the developer."
[Distinguish between internal and external interfaces.]
True
Fals
e
4) The Government Program Office plays a key role in the definition and
control of EXTERNAL interfaces with other program offices that are
responsible for systems or products outside the contractor’s control.
[Describe the role of the Government Program Office in interface management.]
Fals
e
True
5) What key roles are played by an Interface Control Work Group (ICWG)?
Select the three correct answers. [Explain the Interface Management Process functions
of the Interface Control Working Group (ICWG) and various types of interface control
documentation.]
The ICWG is used to control and manage internal
interfaces only.
Performing Architecture Design Process
activities.
Helping to accomplish Interface Management Process
activities.
Helping to develop Interface Control Documents
(ICD).
Scheduling interface management activities.
1) What are the primary purpose(s) of the Risk Management Process?
Select the three correct answers. [Describe the purpose, inputs and outputs, and
activities of the Risk Management Process.]
To provide information of a technical
nature.
To logically analyze product
requirements.
To development mitigation
options.
To implement mitigation options as
needed.
To identify and estimate
uncertainties
2) Which of the following is NOT TRUE about the Risk Management
Process? [Describe how Risk Management is used.] [Remediation Accessed :N]
It is a stand-alone program office
effort.
It is key to achieve program cost, schedule, and technical
performance goals.
Supports a number of other Technical Management
processes.
It is associated with all aspects of the technical
effort.
3) Well-formed, clear risk statements are one of the key outcomes of Risk
Identification. Such statements are characterized by: [Outline the importance of
risk identification.]
A condition as well as a consequence
clause.
A condition clause and a mitigation
option.
A condition clause, mitigation options, and implementation
criteria.
A structured set of mitigation options and their
consequences.
4) Examples of Risk Mitigation techniques include all of the following,
EXCEPT: [Summarize risk mitigation techniques]
Risk rollup
Risk
avoidance
Risk
control
Risk
transfer
Risk
assumption
5) Risk Tracking is accomplished in part by monitoring many of the work
products from Technical Management Processes. [Explain the role of risk tracking.]
True
False
1) Each of these listed activities comprise the Risk Management Process,
EXCEPT: [Describe how Risk Management is used.]
Risk Opportunity
Assessment.
Risk
Identification.
Risk
Analysis.
Risk Mitigation
Planning.
Risk
Tracking.
Risk Mitigation Plan
Implementation
1) The Configuration Management Process supports: Select
the three correct answers. [Describe the purpose, inputs and
outputs, and activities of the Configuration Management Process.]
Collecting stakeholder
requirements.
Proper identification of system
elements.
Consistency between a product and associated
supporting documentation.
Control and documentation of approved
changes.
To realizing Enabling
Products.
2) The function that creates a knowledge base for
performing lifecycle configuration management of a system
is called: [Explain the key functions of Configuration Management.]
Configuration Status
Accounting.
Configuration
Identification.
Configuration
Control.
Configuration Verification and
Audit.
Configuration
Revalidation.
3) Which baseline is directly traceable to the Initial Capabilities Document
(ICD) and describes the system’s performance? [Identify configuration baselines,
how established and their relevance.]
The Functional
Baseline.
The System
Baseline.
The End Product
Baseline.
The Allocated
Baseline.
The Product
Baseline.
4) Which baseline is typically established at the Preliminary Design Review
(PDR)? [Relate Technical Reviews to baselines.]
The Allocated
Baseline.
The Functional
Baseline.
The Development
Configuration.
The End Product
Baseline.
The Product
Baseline.
5) Which of the following verifies that the related design documentation
matches the validated configuration item as specified in the contract?
[Describe the scope and purpose of configuration verifications and audits.]
Physical Configuration Audit
(PCA).
Critical Design Review
(CDR).
System Requirements Review
(SRR).
Preliminary Design Review
(PDR).
Systems Functional Review (SFR).
1) What are the primary purposes of the Technical Data Management
Process? Select the two correct answers. [Describe the purpose, inputs and
outputs, and activities of the Technical Data Management Process]
To identify and quantify technical
uncertainties.
To logically analyze Enabling Product
requirements.
To select criteria for deciding among
alternatives.
To facilitate preparation of necessary reports and
reviews.
To provide technical information to support other
processes.
2) Data needs relating to contractor data should be specified as part of the
Technical Data Management Plan and included in appropriate contractual
documents. [Outline key considerations for Technical Data Management.]
True
Fals
e
3) The Government Program Office’s key considerations in Technical Data
Management should include all of the following, EXCEPT: [Outline key
considerations for Technical Data Management.]
Using "data calls" to maximize the amount of data to be
acquired.
Ensuring the data originator has availability and access permissions to
technical data.
Not imposing changes on existing contractor technical data
management systems, whenever possible.
Accepting data in an Integrated Digital Environment as the preferred
method of delivery considering cost/benefit trades.
1) A purpose of the Technical Assessment Process is to develop the
Systems Engineering Plan. [Describe the purpose, inputs and outputs, and activities of
the Technical Assessment Process.] [Remediation Accessed :N]
Fals
e
True
2) Why is an Integrated Baseline Review (IBR) important for Earned Value
Management (EVM) implementation? [Outline the uses of Earned Value Management
for determining progress against technical plans.]
It confirms that technical scope is fully considered, arranged logically,
and consistent with funding, thus providing a foundation for subsequent
EVM application.
It is held between the Preliminary Design Review (PDR) and the Critical
Design Review (CDR), and it baselines the system prior to detailed design.
It determines if the system structure has been integrated sufficiently to
proceed to the product realization stage so that effective EVM can be used.
It is a technically oriented review that establishes the Actual Cost of
Work Performed (ACWP).
3) A Technical Performance Measurement (TPM) chart that measures the
state of a specific technical parameter usually covers one phase of the
acquisition lifecycle. [Describe the use of Technical Performance Measurement (TPM) for
d
Vista previa del contenido
1) Key output(s) of the Technical Planning Process include: Select the two
correct answers. [Describe the purpose, inputs and outputs, and activities of the Technical
Planning Process.] [Remediation Accessed :N]
Applicable policies, procedures, and
processes
Any previously developed technical
plans
A Test and Evaluation Master Plan
(TEMP)
A Systems Engineering Plan
(SEP)
2) A technical management plan which helps to "ensure that the various
elements of the system are functionally, physically, and electronically
capable of interacting with each other and with all external links" , is the:
[Identify typical technical management plans.]
Interface Management
Plan.
Risk Management
Plan.
Software Development
Plan.
Logistics Support
Plan.
Test and Evaluation Master
Plan.
3) All the following are examples of so-called "specialty technical plans",
EXCEPT for: [Identify specialty engineering technical management plans.]
Acquisition
Strategy.
Security
Plan.
, Programmatic, Environment, Safety, and Occupational Health
(PESHE) Plan.
Producibility
Plan.
Reliability
Plan.
4) Systems Engineering Plan should cover: Select the four correct answers.
[Describe the contents of a Systems Engineering Plan (SEP).]
Systems Engineering
Processes
Enabling facilities for Systems
Engineering
Systems Engineering event
timing
Validation and verification test
scenarios
Enabling Systems Engineering
tools
5) Event-based planning is orchestrated mainly around: Select the two
correct answers. [Explain the difference between event-based and calendar-based
scheduling.] [Remediation Accessed :N]
Technical events and associated
tasks.
Network charts linking task and events by
time.
Time duration and calendar
dates.
Task Entry and Exit criteria.
1) Key input(s) to the Technical Planning Process include: Select the
three correct answers. [Describe the purpose, inputs and outputs, and activities of the
Technical Planning Process.]