Section 1: Inspection Role, Quality and Documentation
1. What is the primary purpose of source inspection of electrical
equipment at the manufacturer's facility?
A. To verify that the equipment conforms to the purchase order,
specifications, and applicable codes before shipment
B. To replace the manufacturer's internal quality control department
C. To install and commission the equipment at the final site
D. To negotiate the final contract price with the manufacturer
Correct Answer: A. To verify that the equipment conforms to the
purchase order, specifications, and applicable codes before shipment
Rationale: Source inspection is a purchaser-side verification that the
equipment is built and tested in accordance with the purchase order, project
specifications, and referenced standards before it leaves the shop. It
supplements, but does not replace, the manufacturer's own QA/QC.
2. Which document defines the inspection and test activities, acceptance
criteria, and the witness and hold points for a purchase order?
A. Commercial invoice
B. Inspection and Test Plan (ITP)
C. Bill of lading
D. Packing list
Correct Answer: B. Inspection and Test Plan (ITP)
Rationale: The ITP (also called a Quality Control Plan) lists each inspection
or test, the governing procedure or standard, acceptance criteria, who
performs it, and whether it is a hold, witness, or review point.
Page 1 of 37
, API SIEE Practice Exam
3. What is a HOLD point in an Inspection and Test Plan?
A. A point reserved for the manufacturer's internal use only
B. A point where only documents are reviewed after the fact
C. A point where the inspector may attend, but work continues if the
inspector is absent
D. A mandatory stop; work may not proceed past it until the inspector has
inspected or released it
Correct Answer: D. A mandatory stop; work may not proceed past it
until the inspector has inspected or released it
Rationale: A hold point cannot be passed without written release from the
designated inspector. Proceeding without release is a nonconformance.
4. What is a WITNESS point in an Inspection and Test Plan?
A. A point where only the manufacturer's records are reviewed
B. A point where work must stop until the inspector's written release is
received
C. A point that applies only to sub-suppliers
D. A point where the inspector is given advance notice and may attend; work
may proceed if the inspector does not attend after proper notification
Correct Answer: D. A point where the inspector is given advance notice
and may attend; work may proceed if the inspector does not attend
after proper notification
Rationale: Witness points require timely notice (the notice period is stated in
the PO or ITP). If the inspector does not attend after proper notice, the
manufacturer may proceed unless the PO says otherwise.
Page 2 of 37
, API SIEE Practice Exam
5. What is the main purpose of a pre-inspection (kick-off) meeting?
A. To start the factory acceptance test without a procedure
B. To align the manufacturer and inspector on scope, specifications, ITP,
test procedures, schedule, and reporting requirements
C. To select the shipping carrier
D. To approve the manufacturer's final invoice
Correct Answer: B. To align the manufacturer and inspector on scope,
specifications, ITP, test procedures, schedule, and reporting
requirements
Rationale: A pre-inspection meeting confirms everyone interprets the
requirements the same way, identifies open items (approved drawings, test
procedures, sub-supplier status), and fixes the inspection schedule before
manufacturing progresses.
6. During an inspection the inspector finds a deviation from the
specification. What is the correct action?
A. Ignore it if the equipment passes the electrical tests
B. Document it on a nonconformance report and ensure the manufacturer
obtains a written disposition from the purchaser or engineering
C. Approve a deviation on the inspector's own authority
D. Verbally accept it if the manufacturer promises to correct it later
Correct Answer: B. Document it on a nonconformance report and
ensure the manufacturer obtains a written disposition from the
purchaser or engineering
Rationale: Inspectors do not grant deviations or waive requirements.
Nonconformances are recorded and dispositioned (repair, rework, reject, or
use-as-is with approval) by the purchaser or engineering.
Page 3 of 37
, API SIEE Practice Exam
7. Why must the inspector verify the calibration status of test
instruments used during acceptance tests?
A. To confirm that measurements are accurate and traceable to national or
international standards
B. To ensure the instruments are the newest model
C. To ensure the instruments are owned by the manufacturer
D. Calibration is only needed for mechanical gauges
Correct Answer: A. To confirm that measurements are accurate and
traceable to national or international standards
Rationale: Test results are only valid if instruments have current calibration
certificates traceable to a recognized standard. Expired or missing calibration
invalidates the results.
8. What does an Inspection Release Note (or Release Certificate)
signify?
A. The inspected equipment has satisfactorily completed the required
inspections and tests and is released for shipment
B. The manufacturer has been paid in full
C. The equipment has been installed and commissioned
D. The warranty period has ended
Correct Answer: A. The inspected equipment has satisfactorily
completed the required inspections and tests and is released for
shipment
Rationale: The release note documents completion of the required
inspection scope and authorizes shipment. It does not relieve the
manufacturer of responsibility for compliance with the order.
Page 4 of 37
API SIEE
Source Inspector Electrical Equipment
Practice Exam: Multiple-Choice Questions with
Answers and Rationales
Section 1: Inspection Role, Quality and Documentation
1. What is the primary purpose of source inspection of electrical
equipment at the manufacturer's facility?
A. To verify that the equipment conforms to the purchase order,
specifications, and applicable codes before shipment
B. To replace the manufacturer's internal quality control department
C. To install and commission the equipment at the final site
D. To negotiate the final contract price with the manufacturer
Correct Answer: A. To verify that the equipment conforms to the
purchase order, specifications, and applicable codes before shipment
Rationale: Source inspection is a purchaser-side verification that the
equipment is built and tested in accordance with the purchase order, project
specifications, and referenced standards before it leaves the shop. It
supplements, but does not replace, the manufacturer's own QA/QC.
2. Which document defines the inspection and test activities, acceptance
criteria, and the witness and hold points for a purchase order?
A. Commercial invoice
B. Inspection and Test Plan (ITP)
C. Bill of lading
D. Packing list
Correct Answer: B. Inspection and Test Plan (ITP)
Rationale: The ITP (also called a Quality Control Plan) lists each inspection
or test, the governing procedure or standard, acceptance criteria, who
performs it, and whether it is a hold, witness, or review point.
Page 1 of 37
, API SIEE Practice Exam
3. What is a HOLD point in an Inspection and Test Plan?
A. A point reserved for the manufacturer's internal use only
B. A point where only documents are reviewed after the fact
C. A point where the inspector may attend, but work continues if the
inspector is absent
D. A mandatory stop; work may not proceed past it until the inspector has
inspected or released it
Correct Answer: D. A mandatory stop; work may not proceed past it
until the inspector has inspected or released it
Rationale: A hold point cannot be passed without written release from the
designated inspector. Proceeding without release is a nonconformance.
4. What is a WITNESS point in an Inspection and Test Plan?
A. A point where only the manufacturer's records are reviewed
B. A point where work must stop until the inspector's written release is
received
C. A point that applies only to sub-suppliers
D. A point where the inspector is given advance notice and may attend; work
may proceed if the inspector does not attend after proper notification
Correct Answer: D. A point where the inspector is given advance notice
and may attend; work may proceed if the inspector does not attend
after proper notification
Rationale: Witness points require timely notice (the notice period is stated in
the PO or ITP). If the inspector does not attend after proper notice, the
manufacturer may proceed unless the PO says otherwise.
Page 2 of 37
, API SIEE Practice Exam
5. What is the main purpose of a pre-inspection (kick-off) meeting?
A. To start the factory acceptance test without a procedure
B. To align the manufacturer and inspector on scope, specifications, ITP,
test procedures, schedule, and reporting requirements
C. To select the shipping carrier
D. To approve the manufacturer's final invoice
Correct Answer: B. To align the manufacturer and inspector on scope,
specifications, ITP, test procedures, schedule, and reporting
requirements
Rationale: A pre-inspection meeting confirms everyone interprets the
requirements the same way, identifies open items (approved drawings, test
procedures, sub-supplier status), and fixes the inspection schedule before
manufacturing progresses.
6. During an inspection the inspector finds a deviation from the
specification. What is the correct action?
A. Ignore it if the equipment passes the electrical tests
B. Document it on a nonconformance report and ensure the manufacturer
obtains a written disposition from the purchaser or engineering
C. Approve a deviation on the inspector's own authority
D. Verbally accept it if the manufacturer promises to correct it later
Correct Answer: B. Document it on a nonconformance report and
ensure the manufacturer obtains a written disposition from the
purchaser or engineering
Rationale: Inspectors do not grant deviations or waive requirements.
Nonconformances are recorded and dispositioned (repair, rework, reject, or
use-as-is with approval) by the purchaser or engineering.
Page 3 of 37
, API SIEE Practice Exam
7. Why must the inspector verify the calibration status of test
instruments used during acceptance tests?
A. To confirm that measurements are accurate and traceable to national or
international standards
B. To ensure the instruments are the newest model
C. To ensure the instruments are owned by the manufacturer
D. Calibration is only needed for mechanical gauges
Correct Answer: A. To confirm that measurements are accurate and
traceable to national or international standards
Rationale: Test results are only valid if instruments have current calibration
certificates traceable to a recognized standard. Expired or missing calibration
invalidates the results.
8. What does an Inspection Release Note (or Release Certificate)
signify?
A. The inspected equipment has satisfactorily completed the required
inspections and tests and is released for shipment
B. The manufacturer has been paid in full
C. The equipment has been installed and commissioned
D. The warranty period has ended
Correct Answer: A. The inspected equipment has satisfactorily
completed the required inspections and tests and is released for
shipment
Rationale: The release note documents completion of the required
inspection scope and authorizes shipment. It does not relieve the
manufacturer of responsibility for compliance with the order.
Page 4 of 37