Examen

Florida Contractor Contract Administration Exam #4 Review 2026 | Practice Questions and Answers

Document preview thumbnail
Vista previa 4 fuera de 71 páginas

Prepare for the Florida Contractor Contract Administration Exam #4 with this focused exam review resource. Review key construction administration concepts, including contract documents, bidding and estimating, permits and inspections, scheduling, change orders, subcontractor coordination, payment procedures, construction liens, project closeout, and regulatory compliance. Practice questions and answers can help reinforce important concepts, assess your understanding, and identify topics that need further review. Suitable for candidates preparing for Florida contractor licensing assessments, this resource complements approved exam references and current licensing guidance.

Vista previa del contenido

Florida Contractor Administration Exam #4 Review 2026 |
Verified Q&A | Graded A+
1. In a project where several glazed fenestration products lack U-factors, what
steps should a contractor take to ensure compliance with Florida's energy
efficiency regulations?

Use the products without any modifications.

Request new U-factors from the manufacturers for all products.

Discard all products without U-factors.

Assign default factors to the products and document them
appropriately.

2. Who is primarily accountable for ensuring that shop drawings meet the
construction criteria?

Subcontractor

Contractor

Architect

Engineer

3. In a scenario where a subcontractor needs to modify their work due to
unforeseen conditions, what steps should the contractor take according to
AIA guidelines?

The building official must be consulted before any changes are
documented.

The subcontractor can directly inform the architect to make changes.

The contractor should issue a change order to document and
authorize the modifications.

, The contractor must seek approval from the owner before any
changes can be made.

4. In which phase of a construction project is the identification of material lead
time crucial?

Scheduling

Estimating

Planning

Networking

5. If a contractor is planning to install electrical service to a new playground,
what steps should they take to ensure compliance with Florida's permit
requirements?

The contractor should only notify the local authorities after the
installation is complete.

The contractor should apply for the necessary electrical permit
before starting the installation.

The contractor should only focus on obtaining permits for structural
elements.

The contractor can proceed without a permit if the project is small.

6. Which type of project is exempt from requiring a local building permit in
Florida?

Being done by the property owner personally

That does not affect public health or safety

Contract for less than $2,500

On state-owned property

,7. If a contractor enters into an oral contract for a project expected to take 400
days, what legal issues might arise in Florida?

The contractor will receive an automatic extension for the project
duration.

The contractor can legally complete the project without any issues.

There are no legal implications for exceeding the time limit.

The contractor may face legal challenges due to exceeding the 365-
day limit for oral contracts.

8. What action can the building official take if work is NOT proceeding to code?

Issue a Stop Work Order

Suspend the contractor's license

Revoke the permit

Arrest the contractor

9. If an owner fails to allow the contractor time to inspect and correct defects
before filing a lawsuit, what potential consequence might they face?

The owner may be required to pay additional fees.

The Building Department may impose fines on the owner.

The lawsuit may be dismissed due to failure to follow proper
procedure.

The contractor may be penalized for not fixing the defect.

10. Describe the primary purpose of the Labor Management Relations Act
(LMRA) in relation to contractors.

, The LMRA focuses on immigration control for workers in the
construction industry.

The Labor Management Relations Act (LMRA) regulates labor
relations and protects the rights of employers and employees in
industries affecting interstate commerce.

The LMRA is concerned with the issuance of building permits.

The LMRA provides guidelines for safety regulations in construction.

11. What is the primary purpose of a permitted site plan in construction?

To guide the contractor in starting the construction process.

To specify the safety regulations for the site.

To outline the financial terms of the contract.

To provide a list of required building permits.

12. A contractor license is required when the total cost, including materials, is
more than

1,000

100

10,000

100,000

13. Which of the following falls under passive design strategy for buildings?

Geometry of the building should allow materials with high heat
capacity to store solar energy during the day and release it in the
evening

Locate the short side of a building on an east-west axis to minimize
solar loads during summer

Información del documento

Subido en
22 de octubre de 2026
Número de páginas
71
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$19.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Vendido
23
Seguidores
1
Artículos
1694
Última venta
1 día hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes