CQM-C CERTIFICATION Questions with Correct Solutions
Question:
1. The ______ consists of daily checks of the work to assure continuing compliance with
contract requirements
Answer:
Follow-up phase
Question:
2. Design-Build contracts require:
Answer:
*The QC Manager to be in place and take an active role in the review and coordination of the
design*
Question:
3. Which of the following is included in all three phases of the Three Phases of Control
Answer:
Safety
Question:
4. The purpose of Construction Quality Management is to
Answer:
*Achieve the quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractor and Government personnel*
Question:
5. Testing is extremely important in Construction Quality Management and is performed by
Answer:
Both the contractor and the Government
Question:
6. The primary purpose of the Three-Phase Control System is to:
Answer:
Require the contractor to plan, schedule, and perform quality management actions to assure
work meets all specified quality standards
Question:
7. Quality Assurance Personnel have the responsibility to:
, Answer:
*require the contractor to maintain the quality specified in the plans and specifications*
Question:
8. the ____ is the appropriate time to assure that all materials and/or equipment have been
tested. submitted, and approved.
Answer:
Preparatory Phase
Question:
9. The Preconstruction Conference and the Coordination and Mutual Understanding Meeting
are:
Answer:
conducted prior to the commencement of any physical construction work
Question:
10. Contractor testing procedures:
Answer:
are specified in the technical specifications, outlined in the Quality Control Plan, and
addressed at the Coordination and Mutual Understanding Meeting.
Question:
11. The Quality Control Plan contains:
Answer:
Identification of individual quality control personnel, including name, qualifications, assigned
duties, responsibilities and authorities
Question:
12. Tests that are unnanounced, randomly performed, and repeat quality control tests are:
Answer:
quality assurance tests
Question:
13. The contractor is required to conduct a preparatory phase meeting before they begins any
definable feature of work except when:
Answer:
there are no exceptions to the rule
Question:
1. The ______ consists of daily checks of the work to assure continuing compliance with
contract requirements
Answer:
Follow-up phase
Question:
2. Design-Build contracts require:
Answer:
*The QC Manager to be in place and take an active role in the review and coordination of the
design*
Question:
3. Which of the following is included in all three phases of the Three Phases of Control
Answer:
Safety
Question:
4. The purpose of Construction Quality Management is to
Answer:
*Achieve the quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractor and Government personnel*
Question:
5. Testing is extremely important in Construction Quality Management and is performed by
Answer:
Both the contractor and the Government
Question:
6. The primary purpose of the Three-Phase Control System is to:
Answer:
Require the contractor to plan, schedule, and perform quality management actions to assure
work meets all specified quality standards
Question:
7. Quality Assurance Personnel have the responsibility to:
, Answer:
*require the contractor to maintain the quality specified in the plans and specifications*
Question:
8. the ____ is the appropriate time to assure that all materials and/or equipment have been
tested. submitted, and approved.
Answer:
Preparatory Phase
Question:
9. The Preconstruction Conference and the Coordination and Mutual Understanding Meeting
are:
Answer:
conducted prior to the commencement of any physical construction work
Question:
10. Contractor testing procedures:
Answer:
are specified in the technical specifications, outlined in the Quality Control Plan, and
addressed at the Coordination and Mutual Understanding Meeting.
Question:
11. The Quality Control Plan contains:
Answer:
Identification of individual quality control personnel, including name, qualifications, assigned
duties, responsibilities and authorities
Question:
12. Tests that are unnanounced, randomly performed, and repeat quality control tests are:
Answer:
quality assurance tests
Question:
13. The contractor is required to conduct a preparatory phase meeting before they begins any
definable feature of work except when:
Answer:
there are no exceptions to the rule