• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 4 fuera de 127 páginas
Examen

Nevada General Engineering Contractor (Class A) Exam Practice Questions and Verified Answers with Rationales

Document preview thumbnail
Vista previa 4 fuera de 127 páginas

Nevada General Engineering Contractor (Class A) Exam Practice Questions and Verified Answers with Rationales

Vista previa del contenido

Nevada General Engineering Contractor
(Class A) Exam Practice Questions and
Verified Answers with Rationales
Question 1
What size marking strip needs to be used when laying foundations or marking
utilities?
Correct Answer
1 inch x 18 inches



Question 2
What should a paving operator do when the asphalt truck is delayed?
Correct Answer
Stop paving to keep the hopper as full as possible



Question 3
What type of material is the appropriate choice for bedding concrete pipe or slab?
Correct Answer
Class A bedding




Page 1 of 127

,Question 4
If one inch of water soaks into the ground in one hour, this is allowable for:
Correct Answer
A seepage pit
Question 1: In Nevada engineering projects, what is the minimum compressive
strength requirement for standard structural concrete used in bridge foundations
unless otherwise specified by the project plans or special provisions?

A. 2,000 psi at 7 days

B. 3,000 psi at 28 days

C. 4,000 psi at 28 days

D. 5,000 psi at 28 days

CORRECT ANSWER: C. 4,000 psi at 28 days

Rationale: Standard structural concrete applications such as bridge foundations and
major structural elements in Nevada Department of Transportation (NDOT)
specifications typically require a minimum 28-day compressive strength of 4,000 psi
to ensure adequate load-bearing capacity and durability against freeze-thaw cycles.

Question 2: According to OSHA and Nevada Division of Industrial Relations
standards, at what trench excavation depth is a protective system (shoring,
shielding, or sloping) mandatory for worker entry, barring solid rock excavation?

A. 3 feet or greater

B. 4 feet or greater

C. 5 feet or greater

D. 8 feet or greater

CORRECT ANSWER: C. 5 feet or greater

Rationale: Under 29 CFR 1926.652 (adopted by Nevada OSHA), excavations 5 feet
(1.5 meters) or deeper require a protective system unless the excavation is made
entirely in stable rock. For excavations less than 5 feet, a competent person may
still require protection if there is potential for cave-in.

Question 3: When performing mass earthwork compaction in arid Nevada soils,
what is the standard moisture content requirement relative to optimum moisture
content determined by AASHTO T 180?

A. Within plus or minus 2 percent of optimum moisture content

B. Within plus or minus 5 percent of optimum moisture content




Page 2 of 127

,C. Exactly equal to optimum moisture content

D. At least 5 percent above optimum moisture content

CORRECT ANSWER: B. Within plus or minus 5 percent of optimum moisture
content

Rationale: Standard earthwork specifications for highway and heavy civil
construction in Nevada typically require subgrade and embankment soils to be
compacted to a specified percentage of maximum dry density with moisture content
controlled within plus or minus 2 to 5 percent of the optimum moisture content
determined by AASHTO T 180 (Modified Proctor) to achieve proper compaction and
prevent excessive settlement or shrinking/swelling.

Question 4: Which of the following contract delivery methods is legally permitted for
Nevada local government public works projects under Nevada Revised Statutes
(NRS) Chapter 338, allowing a single entity to handle both design and
construction?

A. Design-Bid-Build only

B. Construction Manager at Risk (CMAR) and Design-Build

C. Cost-Plus-Percentage-Fee exclusively

D. Time and Materials without a guaranteed maximum price

CORRECT ANSWER: B. Construction Manager at Risk (CMAR) and Design-Build

Rationale: NRS Chapter 338 authorizes public bodies in Nevada to utilize
alternative project delivery methods such as Construction Manager at Risk (CMAR)
and Design-Build, provided specific statutory criteria, approvals, and qualifications-
based selection processes are met.

Question 5: In open-channel flow calculations for drainage design in Nevada flash-
flood prone areas, which empirical formula is most commonly used to estimate
Manning's roughness coefficient (n) for natural unlined earth channels with
moderate vegetation and stones?

A. Hazen-Williams formula

B. Darcy-Weisbach equation

C. Manning's equation

D. Kutter's formula with fixed coefficients

CORRECT ANSWER: C. Manning's equation

Rationale: Manning's equation is universally applied in civil and general engineering
for open-channel flow hydraulics. The roughness coefficient $n$ accounts for
channel bed friction, irregularities, vegetation, and alignment changes.




Page 3 of 127

, Question 6: What is the primary purpose of applying a prime coat to an aggregate
base course prior to placing hot-mix asphalt (HMA) pavement in Nevada roadway
construction?

A. To increase the final pavement thickness

B. To waterproof the subgrade completely

C. To penetrate and bind the loose aggregate particles, promoting adhesion
between the base and asphalt layer

D. To act as a wearing surface for heavy construction traffic before paving

CORRECT ANSWER: C. To penetrate and bind the loose aggregate particles,
promoting adhesion between the base and asphalt layer

Rationale: A prime coat consists of a low-viscosity liquid asphalt sprayed onto an
untreated granular base. Its primary functions are to penetrate the base, seal
capillary voids, bind loose mineral particles, and provide a strong adhesive bond
between the granular base and the subsequent asphalt concrete layer.

Question 7: According to Nevada contractor licensing regulations under Nevada
Administrative Code (NAC) Chapter 624, what is the monetary limit classification
system based upon?

A. The contractor's number of active employees

B. The maximum financial bid or contract limit approved by the Contractors Board
based on financial solvency and working capital

C. The physical size of the contractor's equipment fleet

D. The geographical radius within the state where the contractor is permitted to
operate

CORRECT ANSWER: B. The maximum financial bid or contract limit approved by
the Contractors Board based on financial solvency and working capital

Rationale: The Nevada State Contractors Board (NSCB) assigns a monetary limit to
every contractor's license. This limit restricts the maximum dollar amount (including
labor, materials, and profit) that a licensee can bid on or enter into for a single prime
contract or subcontract, determined by financial statements, net worth, and working
capital.

Question 8: When designing retaining walls in seismic active zones such as the
Basin and Range province of Nevada, which seismic analysis method is
traditionally used to evaluate external stability against sliding and overturning?

A. Coulomb-Rankine static-only method

B. Mononobe-Okabe method

C. Terzaghi one-dimensional consolidation theory



Page 4 of 127

Información del documento

Subido en
18 de octubre de 2026
Número de páginas
127
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$17.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorExpert
3.7
(79)
Vendido
616
Seguidores
315
Artículos
11196
Última venta
2 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes