Examen

C722 Project Management Updated Questions And Correct Answers

Document preview thumbnail
Vista previa 4 fuera de 51 páginas

C722 Project Management Updated Questions And Correct Answers

Vista previa del contenido

C722 PROJECT MANAGEMENT UPDATED QUESTIONS
AND CORRECT ANSWERS
Question:
1. Projects have a(n) ____ start and end date.
a. definite
b. flexible
c. indefinite
Answer:
a. definite

Question:
2. Which of the following are business scenarios?
Choose all that apply.
a. The price of oil is at a five-year high.
b. The price of oil is at a five-year high and is expected
to continue to rise.
c. New battery technology has been developed.
d. New technology can provide smaller batteries that
can be recharged by movement of the mobile device, extending battery life.
Answer:
b. The price of oil is at
a five-year high and is expected to continue to rise.
d. New technology can
provide smaller batteries that can be recharged by movement of the mobile device, extending battery
life.

Question:
3. Projects selected by an organization must be directly related to the organization's ____.
a. strategy
b. operating procedures
c. level of maturity
Answer:
a. strategy

Question:
4. What are the objectives of project management?
a. Meeting scope, budget, and schedule
b. Making sure the guilty are blamed for a problem
c. Maximizing bonuses for successful project comple-
tion
d. Completing the project regardless of whether it
aligns with company strategy
Answer:
a. Meeting scope, budget,
and schedule

,Question:
5. Which criteria should a successful project meet?
a. Overall objectives of the project, regardless of time
taken or budget needed
b. SMART (specific, measurable, achievable, relevant,
and timed) goals
c. Maximizing company profits by taking needed risks
d. Completing the project regardless of whether it
aligns with company strategy
Answer:
b. SMART (specific, mea-
surable, achievable, rele-vant, and timed) goals

Question:
6. Project managers (PMs) must not only manage people of all levels, but they must also manage
costs, expecta-tions, procurement, outside suppliers, and partners. True False
Answer:
True

Question:
7. It is important that project status meetings are ____.
a. regular and timely
b. weekly
c. monthly
d. at stakeholders' request
Answer:
a. regular and timely

Question:
8. Which communication type is the best option when working in a widely dispersed virtual team?
a. Point-to-point instant messaging
b. Phone calls
c. Shared threaded discussion
d. Email
Answer:
c. Shared threaded dis-
cussion

Question:
9. Which organization includes standards for the Or-ganizational Project Management Maturity
Model (OPM3)?
a. PMI
b. APM
c. IPMA
d. AXELOS Ltd.
Answer:
a. PMI

,Question:
10. Which organization provides the Project Management Professional (PMP) certification?
a. PMI
b. APM
c. IPMA
d. AXELOS Ltd.
Answer:
a. PMI

Question:
11. Which organizational structure is used by government entities?
a. Projectized
b. Functional
c. Matrix
Answer:
b. Functional

Question:
12. Which statement is true about the project manage-ment office (PMO)? Choose all that apply.
a. The PMO tracks "lessons learned" to be carried to
new projects.
b. The PMO consists of employees who cannot be
dismissed from the organization.
c. The PMO helps provide resources to projects as
needed.
d. The PMO creates a repository for all project knowl-
edge in the organization.
Answer:
a. The PMO tracks "lessons
learned" to be carried to new projects.
c. The PMO helps provide
resources to projects as needed.
d. The PMO creates a
repository for all project knowledge in the organi-zation.

Question:
13. The project management offices (PMOs) can help align project investment to ____.
a. historical records
b. monitoring and control
c. corporate strategy
d. project policies
Answer:
c. corporate strategy

Question:
14. In addition to the triple constraints, what other con-siderations may determine if a project is
successful?
a. The project is of high interest to the CEO.

, b. No government regulations affect the product of
the project.
c. The requirements in the scope adequately define
the project's objectives.
Answer:
c. The requirements in the
scope adequately define the project's objectives.

Question:
15. Which statement about projects, programs, and port-folios is correct?
a. A group of programs or projects that support the
same business goal makes up a portfolio.
b. Any two projects can make up a program.
c. Calling an endeavor a program justifies assigning
more resources.
d. Only programs can be a part of a portfolio.
Answer:
a. A group of programs
or projects that support the same business goal makes up a portfolio.

Question:
16. You work at an automotive manufacturer. This compa-ny has the goal of being able to supply a
full range of passenger cars, from small compact to large luxury. A huge endeavor is being
undertaken to design and develop an entirely new small passenger car. There are several groups of
people working on different aspects of this endeavor: one group on the engine, one on the
transmission, one on the navigation system, and so on. Each group has its scheduled start and end
dates and a definition of the unique product it will create. Each of these groups is working on a ____.
a. program
b. portfolio
c. project
d. long-term business strategy
Answer:
c. project

Question:
17. You are talking to a friend who has renovation project management experience. You cannot
decide whether you want to take on the daunting task of being your own project manager. Your friend
tells you that if you decide to manage the project, your first assignment will be to create the project
____.
a. scheduling template
b. workflow diagram
c. platform
d. plan
Answer:
d. plan

Question:
18. Which skills do you think are critical in a project man-agement role? Choose all that apply.

Información del documento

Subido en
15 de octubre de 2026
Número de páginas
51
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$20.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Briwisescore
2.5
(2)
Vendido
43
Seguidores
5
Artículos
17694
Última venta
2 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes