ATSSA TRAFFIC CONTROL SUPERVISOR "THE TYPICAL PROJECT" MODULE 7 Questions with Correct Solutions Question: 1. Planning Answer: What stage: Gather available data Prior to occupying TTC zone Consider the needs of all users Coordinate between adjacent or overlapping projects Question: 2. Design Answer: What stage: Select best traffic control alternative based on: safety, mobility, cost, constructability Question: 3. Traffic Factors, characteristics, and speed. Traffic controls, urban features, and traffic generators Answer: What Factors effect the design of a TTC plan Question: 4. What are the MUTCD categories of Work Duration? Answer: Long-term stationary Intermediate-term stationary short-term stationary short-duration mobile Question: 5. Occupies location more than 3 days larger channelizing devices and post mounted signs conflicting roadway markings removed and replaced with temporary markings cover or remove conflicting signage Answer: Long-term stationary (MUTCD work duration category) Question: 6. More than 1 day, less than 3 days Nightime work of more than 1 hour Answer: Intermediate-stationary (MUTCD work duration category)

Vista previa del contenido

ATSSA TRAFFIC CONTROL SUPERVISOR "THE TYPICAL
PROJECT" MODULE 7 Questions with Correct Solutions


Question:
1. Planning

Answer:
What stage: Gather available data Prior to occupying TTC zone Consider the needs of all
users Coordinate between adjacent or overlapping projects


Question:
2. Design

Answer:
What stage: Select best traffic control alternative based on: safety, mobility, cost,
constructability


Question:
3. Traffic Factors, characteristics, and speed. Traffic controls, urban features, and traffic
generators

Answer:
What Factors effect the design of a TTC plan


Question:
4. What are the MUTCD categories of Work Duration?

Answer:
Long-term stationary Intermediate-term stationary short-term stationary short-duration
mobile


Question:
5. Occupies location more than 3 days larger channelizing devices and post mounted signs
conflicting roadway markings removed and replaced with temporary markings cover or
remove conflicting signage

Answer:
Long-term stationary (MUTCD work duration category)


Question:
6. More than 1 day, less than 3 days Nightime work of more than 1 hour

Answer:
Intermediate-stationary (MUTCD work duration category)

, Question:
7. Daytime work 1 to 12 hours cones and portable signs

Answer:
Short-term stationary (MUTCD work duration category)


Question:
8. work that moves intermittently or continuously May use truck-mounted impact attenuators

Answer:
Mobile (MUTCD work duration category)


Question:
9. Constructability

Answer:
Nature of the work access requirements drainage issues, drainage during construction
construction equipment size of work space Access to work area room to maneuver equipment


Question:
10. Outside the shoulder On the shoulder with no encroachment on the shoulder with minor
encroachment within the median within the traveled way

Answer:
MUTCD "Locations of work"


Question:
11. Phasing

Answer:
Refers to TTC projects being broken into multiple steps Could be dangerous due to devices
and workers on the move coordination and timing are key


Question:
12. Public relations

Answer:
Working with the media News announcements Phone hotline door hangers / notices PCMS
one of the TMP (Transportation Management Plan) requirements


Question:
13. Notify Those affected Pre-con meeting Inspection before delivery of devices

Answer:
Pre-construction activities

Información del documento

Subido en
14 de octubre de 2026
Número de páginas
6
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$8.39

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
VictorGrades
5.0
(1)
Vendido
24
Seguidores
0
Artículos
1887
Última venta
1 mes hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes