2a Hoisting license.Final Test Paper 2026\2027.
2a Hoisting license
What is the purpose of the swing gear on an excavator
It connects the car body to the tracks
Who is responisble for inspecting a trench before
anyone goes in it
The equipment operator
What is the prefered sling angle
60*
The top of the spoil pile is called
The crown
A four footbdeep trench requires an additional ladder
for each _ of open trench
25ft
Materials mist be kept back from the edge of the
trenxh a minimum of
Two feet
When can inspector revoke a hoistinf licence
Failure to pay excise tax
Who developed the ma crane hand signals
Ansi / asme
Dot stands for
,2a Hoisting license.Final Test Paper 2026\2027.
Department of transportion
When do you do your walk around of the equpiment
Before you start it
In the one to one sloping ratio what does the 2nd one
represent
Depth or verticle rise
On a track machine the gears should be where
In the rear
When load leveling when do you deploy your
stablizers
Before you make the lift
When backfilling an excavation you should use a
Small lift , shade the ditch
In the state of MA what criteria require a hoisting
license
More than 500lbs
Height greater than 10ft
Bucket bigger than 1/4 yard
What tyoe of saftey system isnused on de-energized
circuts
Lockout tag out total de energization
In what time should you contact departmant of public
safety if a death occurs
Withen one hour
, 2a Hoisting license.Final Test Paper 2026\2027.
How many lbs in 1 ton
2000
All welding and cutting on hoistinf equipment shall be
done in accoradance with the requirments of what
Aws Asme codes
What items should be checked on a daily basis
Fluid levels, hoses tires belts horn backup system brakes
and controls
What action does a signal person intend the operator
to preform if he extends his arm at shoulder height
makes a fist with his hands and sticks his thumb up
Boom up
What type of protections should be given to operators
Protection from weather
Saftey glass
Heat in cold weather
Over head protection
What law governs hoisting equipment in state of ma
Chapter 146 of general laws 530 cmr section 6
How do you test the load brake on a LULL
Lift the load just off the ground and return the boom
handle to the neutral postion
How do you find the weight of a load
2a Hoisting license
What is the purpose of the swing gear on an excavator
It connects the car body to the tracks
Who is responisble for inspecting a trench before
anyone goes in it
The equipment operator
What is the prefered sling angle
60*
The top of the spoil pile is called
The crown
A four footbdeep trench requires an additional ladder
for each _ of open trench
25ft
Materials mist be kept back from the edge of the
trenxh a minimum of
Two feet
When can inspector revoke a hoistinf licence
Failure to pay excise tax
Who developed the ma crane hand signals
Ansi / asme
Dot stands for
,2a Hoisting license.Final Test Paper 2026\2027.
Department of transportion
When do you do your walk around of the equpiment
Before you start it
In the one to one sloping ratio what does the 2nd one
represent
Depth or verticle rise
On a track machine the gears should be where
In the rear
When load leveling when do you deploy your
stablizers
Before you make the lift
When backfilling an excavation you should use a
Small lift , shade the ditch
In the state of MA what criteria require a hoisting
license
More than 500lbs
Height greater than 10ft
Bucket bigger than 1/4 yard
What tyoe of saftey system isnused on de-energized
circuts
Lockout tag out total de energization
In what time should you contact departmant of public
safety if a death occurs
Withen one hour
, 2a Hoisting license.Final Test Paper 2026\2027.
How many lbs in 1 ton
2000
All welding and cutting on hoistinf equipment shall be
done in accoradance with the requirments of what
Aws Asme codes
What items should be checked on a daily basis
Fluid levels, hoses tires belts horn backup system brakes
and controls
What action does a signal person intend the operator
to preform if he extends his arm at shoulder height
makes a fist with his hands and sticks his thumb up
Boom up
What type of protections should be given to operators
Protection from weather
Saftey glass
Heat in cold weather
Over head protection
What law governs hoisting equipment in state of ma
Chapter 146 of general laws 530 cmr section 6
How do you test the load brake on a LULL
Lift the load just off the ground and return the boom
handle to the neutral postion
How do you find the weight of a load