Pmt 3600V Final Exam Prep Questions And Answers With Verified Solutions 2026/2027 Update. Just Released

Document preview thumbnail
Vista previa 3 fuera de 24 páginas

PMT 3600V FINAL EXAM PREP QUESTIONS AND ANSWERS WITH VERIFIED SOLUTIONS 2026/2027 UPDATE. JUST RELEASED

Vista previa del contenido

PMT 3600V FINAL EXAM PREP
QUESTIONS AND ANSWERS WITH
VERIFIED SOLUTIONS 2026/2027
UPDATE. JUST RELEASED


1. A project has a Budget at Completion (BAC) of $1,000,000 and an Earned Value (EV) of

$400,000. If the Actual Cost (AC) is $500,000, what is the To-Complete Performance Index

(TCPI) based on the BAC?

A. 0.80


B. 1.20


C. 1.25


D. 1.00


Answer: B


Conceptual Explanation: TCPI (BAC) = (BAC - EV) / (BAC - AC). So, (1,000,000 - 400,000)

/ (1,000,000 - 500,000) = 600,,000 = 1.2.


2. Which technical review is conducted to ensure the system can proceed into fabrication,

assembly, integration, and testing within cost and schedule constraints?

A. Critical Design Review (CDR)


B. Preliminary Design Review (PDR)

,C. System Requirements Review (SRR)


D. Production Readiness Review (PRR)


Answer: A


Conceptual Explanation: The Critical Design Review (CDR) determines if the system

design is appropriately mature to proceed into full-scale fabrication and assembly.


3. In an FPIF (Fixed Price Incentive Firm) contract, what happens if the actual cost exceeds the

price ceiling?

A. The government pays the difference.


B. The contractor is paid the target profit only.


C. The price is renegotiated to a Cost Plus format.


D. The contractor bears all costs above the ceiling price.


Answer: D


Conceptual Explanation: In Fixed Price Incentive Firm contracts, the price ceiling is the

maximum amount the government will pay; all costs beyond that are the contractor’s

responsibility.


4. Which risk handling strategy involves changing the project plan to eliminate the threat

entirely?

A. Mitigation


B. Acceptance

, C. Transfer


D. Avoidance


Answer: D


Conceptual Explanation: Risk avoidance involves changing the project management plan

to eliminate the threat posed by an adverse risk.


5. What is the primary difference between Management Reserve (MR) and Contingency

Reserve?

A. MR is for ‘known unknowns’, Contingency is for ‘unknown unknowns’.


B. Contingency Reserve is held by the customer, MR is held by the PM.


C. MR is part of the Performance Measurement Baseline (PMB).


D. MR is for ‘unknown unknowns’, Contingency is for ‘known unknowns’.


Answer: D


Conceptual Explanation: Contingency reserve is for identified risks (known unknowns)

and is part of the PMB. Management Reserve is for unidentified risks (unknown unknowns)

and is not part of the PMB.


6. If a task on the critical path is delayed by 3 days, what is the effect on the overall project

completion date?

A. The project will be delayed by 3 days.


B. No effect if there is free float.

Información del documento

Subido en
23 de septiembre de 2026
Número de páginas
24
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheStar
3.7
(140)
Vendido
736
Seguidores
178
Artículos
28662
Última venta
1 día hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes