Pmt 3600V Comprehensive Exam Review Questions And Answers With Verified Solutions 2026/2027 Update. Just Released

Document preview thumbnail
Vista previa 3 fuera de 24 páginas

PMT 3600V COMPREHENSIVE EXAM REVIEW QUESTIONS AND ANSWERS WITH VERIFIED SOLUTIONS 2026/2027 UPDATE. JUST RELEASED

Vista previa del contenido

PMT 3600V COMPREHENSIVE EXAM
REVIEW QUESTIONS AND ANSWERS
WITH VERIFIED SOLUTIONS 2026/2027
UPDATE. JUST RELEASED


1. If the Budgeted Cost of Work Performed (BCWP) is $450,000 and the Budgeted Cost of

Work Scheduled (BCWS) is $500,000, what is the Schedule Performance Index (SPI)?

A. 1.05


B. 1.11


C. -$50,000


D. 0.90


Answer: D


Conceptual Explanation: SPI is calculated as BCWP divided by BCWS (450,,000

= 0.90). An SPI less than 1.0 indicates the project is behind schedule.


2. Which cost estimating method is typically used during the earliest stages of an acquisition

program when little technical detail is available?

A. Engineering Bottom-Up


B. Actual Costs


C. Parametric

,D. Analogy


Answer: D


Conceptual Explanation: The Analogy method compares a new system with a similar

legacy system and is used early in the lifecycle when technical data is sparse.


3. In the context of Earned Value Management, what does ‘Management Reserve’ (MR)

represent?

A. Budget for scope changes not yet identified


B. Budget for risks identified in the Risk Register


C. Budget held for unknown unknowns within the existing scope


D. Profit for the contractor


Answer: C


Conceptual Explanation: Management Reserve is budget withheld for management

control purposes for unforeseen work that is within the scope of the contract (unknown

unknowns).


4. A project has a BAC of $1,000,000 and a cumulative CPI of 0.80. Assuming future work will

be performed at the current efficiency rate, what is the Estimate at Completion (EAC)?

A. $800,000


B. $1,250,000


C. $1,000,000

, D. $1,200,000


Answer: B


Conceptual Explanation: EAC = BAC / CPI. In this case, $1,000,.80 = $1,250,000.


5. Which contract type places the maximum risk and full responsibility for all costs and

resulting profit or loss on the contractor?

A. Firm Fixed Price (FFP)


B. Fixed Price Incentive Firm (FPIF)


C. Cost Plus Fixed Fee (CPFF)


D. Cost Plus Award Fee (CPAF)


Answer: A


Conceptual Explanation: In a Firm Fixed Price (FFP) contract, the price is not subject to

adjustment, placing all cost risk on the contractor.


6. What is the primary purpose of an Integrated Baseline Review (IBR)?

A. To achieve a mutual understanding of the performance measurement baseline and risks


B. To finalize the contract price


C. To audit the contractor’s accounting system


D. To penalize the contractor for schedule delays


Answer: A

Información del documento

Subido en
23 de septiembre de 2026
Número de páginas
24
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheStar
3.7
(140)
Vendido
736
Seguidores
178
Artículos
28662
Última venta
1 día hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes