MGSC 395 EXAM II | UPDATED Questions with 100% Verified
Answers
Question:
WORK CONTENT of an Activity
Answer:
activity time x (1 + fraction rework)
Question:
Capacity of a Resource Pool
Answer:
(# resource units x availability x load batch)/ resource unit load
Question:
Takt time
Answer:
total production time available per day (sec)/ Daily Demand
Question:
Pitch
Answer:
Takt time x finished product tray size
Question:
Bill of Materials Ratio (BOM)
Answer:
how many units the part are required for one unit of the Finished Product
Question:
Total Inventory Flow Time
Answer:
total of all RM, WIP, & FG Inventory Days
, Question:
Daily Production Capacity (units/day)
Answer:
[total day's production available seconds x fractional uptime] / [A x BOM ratio]
Question:
A=
Answer:
[cycle time x ( 1+fraction scrap)/(number of operators)] + [batch set up time/ batch load]
** if batch size is 1, stop after first section
Question:
Turnaround Time to be Promised for a New Order Size (TAT)
Answer:
Total Inventory Flow Time + [Q/ Daily production capacity of the Bottleneck]
Question:
Cycle time
Answer:
(production available in seconds or minutes) / (target production rate)
Question:
Nt (theoretical minimum number of workstations)
Answer:
Total of All Task Times/ Cycle Time
Question:
Goal of Lean systems:
Answer:
1. reduce inventory and other forms of buffer that hide uncertainties and inefficiencies in a
manufacturing/ service organization.
2. to improve the efficiency and speed of processes to produce more faster with less
resources.
Answers
Question:
WORK CONTENT of an Activity
Answer:
activity time x (1 + fraction rework)
Question:
Capacity of a Resource Pool
Answer:
(# resource units x availability x load batch)/ resource unit load
Question:
Takt time
Answer:
total production time available per day (sec)/ Daily Demand
Question:
Pitch
Answer:
Takt time x finished product tray size
Question:
Bill of Materials Ratio (BOM)
Answer:
how many units the part are required for one unit of the Finished Product
Question:
Total Inventory Flow Time
Answer:
total of all RM, WIP, & FG Inventory Days
, Question:
Daily Production Capacity (units/day)
Answer:
[total day's production available seconds x fractional uptime] / [A x BOM ratio]
Question:
A=
Answer:
[cycle time x ( 1+fraction scrap)/(number of operators)] + [batch set up time/ batch load]
** if batch size is 1, stop after first section
Question:
Turnaround Time to be Promised for a New Order Size (TAT)
Answer:
Total Inventory Flow Time + [Q/ Daily production capacity of the Bottleneck]
Question:
Cycle time
Answer:
(production available in seconds or minutes) / (target production rate)
Question:
Nt (theoretical minimum number of workstations)
Answer:
Total of All Task Times/ Cycle Time
Question:
Goal of Lean systems:
Answer:
1. reduce inventory and other forms of buffer that hide uncertainties and inefficiencies in a
manufacturing/ service organization.
2. to improve the efficiency and speed of processes to produce more faster with less
resources.