Examen

Cm 4101 Module 2 P6 Lab Project Quiz | Primavera P6 Activity Relationships, Wbs & Lag – Comprehensive Questions And Answers | Verified And Welldetailed Answers | Detailed Explanations And Rationales | Complete Exam Preparation Study Guide | Practice

Document preview thumbnail
Vista previa 4 fuera de 31 páginas

CM 4101 MODULE 2 P6 LAB PROJECT QUIZ | PRIMAVERA P6 ACTIVITY RELATIONSHIPS, WBS & LAG – COMPREHENSIVE QUESTIONS AND ANSWERS | VERIFIED AND WELLDETAILED ANSWERS | DETAILED EXPLANATIONS AND RATIONALES | COMPLETE EXAM PREPARATION STUDY GUIDE | PRACTICE QUESTIONS | LATEST EXAM UPDATE

Vista previa del contenido

CM 4101 MODULE 2 P6 LAB PROJECT QUIZ | PRIMAVERA P6 ACTIVITY RELATIONSHIPS,
WBS & LAG – COMPREHENSIVE QUESTIONS AND ANSWERS | VERIFIED AND
WELLDETAILED ANSWERS | DETAILED EXPLANATIONS AND RATIONALES | COMPLETE
EXAM PREPARATION STUDY GUIDE | PRACTICE QUESTIONS | LATEST EXAM UPDATE

* FRONT MATTER *

CORE DOMAINS

• Primavera P6 project and activity fundamentals
• Work Breakdown Structure (WBS)
• Activity identification and organization
• Predecessor and successor relationships
• Finish-to-Start, Start-to-Start, Finish-to-Finish, and Start-to-Finish logic
• Relationship lag and lead
• Activity Network and Gantt Chart logic
• Schedule logic, float, and critical-path implications
• Relationship configuration and schedule quality checks
• Practical P6 project-planning and scheduling applications

INTRODUCTION

This assessment develops comprehensive knowledge and practical understanding of
Primavera P6 project scheduling, with particular emphasis on activity relationships, Work
Breakdown Structure (WBS), and lag. The questions assess terminology, logical relationships,
activity sequencing, WBS organization, schedule interpretation, configuration procedures,
and practical decision-making. Multiple-choice questions are used to test both foundational
knowledge and the ability to apply scheduling concepts to realistic project situations.
Understanding these concepts is essential because P6 relationships and activity durations
work together to determine schedule dates, while WBS provides a structured framework for
organizing project scope and activities. The assessment therefore emphasizes accurate
interpretation, logical reasoning, and effective application of P6 scheduling principles.

SECTION ONE: QUESTIONS 1–100

PRIMAVERA P6 FUNDAMENTALS AND ACTIVITY RELATIONSHIPS

Question 1. What is the primary purpose of an activity relationship in Primavera P6?

A. To assign a resource price to an activity
B. To define logical dependency between activities
C. To calculate the activity's budget automatically
D. To identify the project's organizational owner

Correct Answer: B. To define logical dependency between activities

,Explanation: An activity relationship establishes how one activity is logically connected to
another. These relationships form the project network and, together with activity durations,
influence schedule dates.



Question 2. In a relationship between two activities, what is the predecessor?

A. The activity that follows another activity
B. The activity with the longest duration
C. The activity that logically precedes another activity
D. The activity with the highest cost

Correct Answer: C. The activity that logically precedes another activity

Explanation: The predecessor is the activity whose start or finish provides the logical
reference for the successor activity.



Question 3. What is a successor activity?

A. An activity that logically follows another activity
B. An activity assigned to the highest WBS level
C. An activity with no predecessor
D. An activity containing a constraint

Correct Answer: A. An activity that logically follows another activity

Explanation: A successor is the activity whose timing is logically dependent on the
predecessor according to the defined relationship.



Question 4. Which relationship type is the default relationship type in Primavera P6?

A. Start to Start
B. Finish to Finish
C. Start to Finish
D. Finish to Start

Correct Answer: D. Finish to Start

Explanation: Primavera P6 identifies Finish-to-Start (FS) as the default relationship type.



Question 5. What does a Finish-to-Start relationship mean?

,A. The successor cannot start until the predecessor finishes
B. The successor cannot finish until the predecessor starts
C. Both activities must finish simultaneously
D. Both activities must start simultaneously

Correct Answer: A. The successor cannot start until the predecessor finishes

Explanation: In an FS relationship, the predecessor's finish controls the earliest possible start
of the successor.



Question 6. Which relationship allows two activities to begin based on the start of the
predecessor?

A. Finish to Finish
B. Start to Start
C. Finish to Start
D. Start to Finish

Correct Answer: B. Start to Start

Explanation: A Start-to-Start relationship establishes the successor's start in relation to the
predecessor's start.



Question 7. Which relationship connects the finish of the predecessor to the finish of the
successor?

A. Finish to Finish
B. Finish to Start
C. Start to Start
D. Start to Finish

Correct Answer: A. Finish to Finish

Explanation: In an FF relationship, the finish of the successor is logically dependent on the
finish of the predecessor.



Question 8. Which relationship means that the successor cannot finish until the
predecessor starts?

A. Finish to Start
B. Start to Start
C. Finish to Finish
D. Start to Finish

, Correct Answer: D. Start to Finish

Explanation: Start-to-Finish is defined as a relationship in which the successor cannot finish
until the predecessor starts.



Question 9. Which relationship is generally represented by the abbreviation FS?

A. Finish to Start
B. Finish Sequence
C. Final Schedule
D. Finish Standard

Correct Answer: A. Finish to Start

Explanation: FS is the standard abbreviation for Finish-to-Start activity logic.



Question 10. Which abbreviation represents Start-to-Start logic?

A. FF
B. SS
C. SF
D. FS

Correct Answer: B. SS

Explanation: SS represents Start-to-Start, meaning the successor's start is logically tied to
the predecessor's start.



Question 11. Which abbreviation represents Finish-to-Finish logic?

A. FF
B. FS
C. SF
D. SS

Correct Answer: A. FF

Explanation: FF represents Finish-to-Finish logic.



Question 12. Which abbreviation represents Start-to-Finish logic?

A. SS
B. FS

Información del documento

Subido en
18 de septiembre de 2026
Número de páginas
31
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$21.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
0
Seguidores
0
Artículos
477
Última venta
14 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes