Total Costs of Ownership - ANSWER-Which term means the total cost to the
Government of acquiring, operating, supporting, and (if applicable) disposing of
the items being acquired?
Life-Cycle Costs - ANSWER-The total cost of acquiring, operating, supporting,
and disposing.
Contracting Officer's Representative - ANSWER-Who is the individual designated
and authorized in writing by the contracting officer to perform specific technical or
administrative functions?
,Contracting Officer's Policy - ANSWER-It is the Government's policy that before
executing a contract, the contracting officer must obtain written assurance from the
responsible fiscal authority that adequate funds are available.
Preferred Acquisition Method - ANSWER-What would be the preferred way to
acquire an item in Government contracting? b. Purchase the requirement as a
commercial item.
Government Property Provision - ANSWER-Contracting officers shall provide
property to contractors only when it is clearly demonstrated that the overall benefit
to the acquisition significantly outweighs the increased cost of administration.
Acquisition Planning Start - ANSWER-Acquisition planning should begin as soon
as the agency need is identified.
Cost or Pricing Data Exception - ANSWER-Which of the following is an
exception to obtaining certified cost or pricing data? a. Adequate price
competition.
Encouraging Small Business Participation - ANSWER-The contracting officer
shall take actions to encourage small business participation in acquisitions by
dividing acquisitions into reasonably small lots to permit offers on quantities less
than the total requirement.
Solicitation Amendment - ANSWER-Which offerors receive an amendment on a
solicitation that has yet to close? c. All parties receiving the solicitation.
Industry Information Exchange Purpose - ANSWER-The purpose of exchanging
information with industry before receipt of proposals is to improve the
understanding of Government requirements and industry capabilities.
,Solicitation Title for Negotiated Procedures - ANSWER-Which of the following is
the correct title of a solicitation for negotiated procedures? a. Invitation for
Proposals.
Request for Proposals - ANSWER-The correct title of a solicitation for negotiated
procedures.
Expected to exceed $25,000 - ANSWER-The dollar value at which a contracting
officer must synopsize a proposed contract action in the Governmentwide point of
entry (GPE).
Invitations for bids (IFBS) - ANSWER-A method used to solicit bids for contracts.
Types of contracts awarded from IFBS - ANSWER-FFP or FP-EPA
Contracting officer requirements before signing a contract - ANSWER-Ensure that
all statutory requirements have been met and try to ensure all regulations or
applicable procedures have been followed.
Status of the contract when solicitation provisions are being selected - ANSWER-
Pre-Award
Type of termination for a contractor failing to deliver on time - ANSWER-
Termination for Cause.
Number of parts in the FAR - ANSWER-53
, DoD Procurement Instrument Identifier (PIID) length - ANSWER-13 positions
long.
Position 9 in PIID when it is a 'D' - ANSWER-Indefinite-delivery contracts to
include IDIQs and requirements contracts.
Authority of a Contracting Officer's Representative (COR) - ANSWER-Designated
in writing, with a copy given to the contractor and contract administration office.
Event to aid Government and contractor personnel after contract award -
ANSWER-Post-award orientation conference.
Tool used by DoD for structured profit analysis - ANSWER-DD Form 1547,
Weighted Guidelines Method.
Contract types for acquiring commercial items of supply - ANSWER-Only firm-
fixed-price contracts or fixed-price contracts with economic price adjustment.
Application of a contract clause - ANSWER-A contract clause applies unless
superseded by a solicitation provision.
Termination for Convenience - ANSWER-A type of contract termination that
allows the government to end a contract without cause.
Termination for Default - ANSWER-A type of termination due to the contractor's
failure to perform.