Examen

Ops 571 Final Exam 3 – Question And Answers

Document preview thumbnail
Vista previa 4 fuera de 62 páginas

OPS 571 FINAL EXAM 3 – QUESTION AND ANSWERS Questions 1–180 | Operations Management | 100% Pass Guaranteed | Graded A+

Vista previa del contenido

1



OPS 571 FINAL EXAM 3 – QUESTION AND ANSWERS
Questions 1–180 | Operations Management | 100% Pass Guaranteed | Graded A+



1. According to your text, the most common process metric is:

A. Productivity
B. Efficiency
C. Utilization
D. Throughput time

Correct answer: C
Explanation: Utilization is the most common process metric. It is defined as the ratio
between the actual amount of time a resource is activated for and the total amount of
time the resource is available for use. This metric helps operations managers understand
how effectively their resources are being used .



2. __________ is when the activities in the stage must stop because there is no place
to deposit the item just completed.

A. Starving
B. Buffering
C. Blocking
D. Pacing

Correct answer: C
Explanation: Blocking occurs when activities in a stage must stop because there is no
place to deposit the item just completed. This is a common issue in production lines
where the next stage cannot accept the completed work, causing the previous stage to
halt operations .



3. The average time between completion of units is commonly known as:

A. Cycle time
B. Throughput time
C. Operation time
D. Run time

, 2


Correct answer: A
Explanation: Cycle time is the average time between completion of units. It is a
fundamental measure in operations management that helps determine production
capacity and scheduling requirements .



4. According to Hayes and Wheelwright, which of the following is not a major
process flow structure?

A. Assembly Line
B. Job Shop
C. Batch
D. Project

Correct answer: D
Explanation: According to Hayes and Wheelwright, the major process flow structures
are Job Shop, Batch, Assembly Line, and Continuous Flow. Project is a type of
organizational structure, not a process flow structure in their framework .



5. The best process flow structure to use for making automobiles is:

A. Group technology cell
B. Job Shop
C. Batch Shop
D. Assembly Line

Correct answer: D
Explanation: The assembly line is the best process flow structure for making
automobiles because it involves producing discrete products at a controlled rate through
a standardized sequence of operations. This allows for high-volume, efficient production
of complex products .



6. The type of processing structure that is used to produce gasoline, chemicals, and
steel is:

A. Assembly Line
B. Job Shop

, 3


C. Batch
D. Continuous Flow

Correct answer: D
Explanation: Continuous flow is used for producing gasoline, chemicals, and steel.
These are products that are produced in a continuous, non-discrete manner with highly
standardized processes and very high volumes .



7. When evaluating a new product development project using net present value
analysis, which of the following will make the project more attractive?

A. Delaying the start of the project
B. Making the project run over a longer period of time
C. Improving (bringing forward) the date when revenue will begin
D. A and B

Correct answer: C
Explanation: Bringing forward the date when revenue will begin increases the net
present value of a project because it reduces the time value of money discount applied to
future cash flows. Delaying the start (A) and extending the project duration (B) would
both decrease NPV .



8. The most important performance dimension for product development projects is:

A. Quality
B. Time-to-market
C. Productivity
D. Product flexibility

Correct answer: B
Explanation: Time-to-market is considered the most important performance dimension
for product development projects because it directly impacts a company's ability to
capture market share and respond to customer needs before competitors .



9. In which phase of new-product design process are considerations to target market,
desired level of performance, investment requirements and financial impact made:

, 4


A. Concept development
B. Product planning
C. Product/process engineering
D. Pilot production/testing

Correct answer: B
Explanation: Product planning is the phase where considerations to target market,
desired level of performance, investment requirements, and financial impact are made.
This phase bridges the concept and detailed design phases .



10. A major competitive dimension that forms a company's strategic operational
competitive position in their strategic planning is which of the following?

A. Cost or price
B. Focus
C. Straddling
D. Automation

Correct answer: A
Explanation: Cost or price is a major competitive dimension that forms a company's
strategic operational competitive position. Companies can compete on cost leadership,
differentiation, or focus, with cost/price being a fundamental dimension .



11. In setting up a kanban control system, you need to determine the number of
kanban card sets needed. If the expected demand during lead time is 25 per hour,
the safety stock is 20 percent of the demand during lead time, the container size is
5, and the lead time to replenish an order is 5 hours, what is the number of kanban
card sets needed?

A. 27
B. 20
C. 5
D. 30

Correct answer: D
Explanation: The formula for kanban card sets is: N = (D × L + S) / C, where D is demand
per hour, L is lead time, S is safety stock, and C is container size. N = (25 × 5 + 0.20 × 25 ×
5) / 5 = (125 + 25) / 5 = = 30. Therefore, 30 kanban card sets are needed .

Información del documento

Subido en
10 de septiembre de 2026
Número de páginas
62
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$16.79

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
1
Seguidores
0
Artículos
173
Última venta
4 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes