Number of mortar compression tests taken per day for
|\ |\ |\ |\ |\ |\ |\ |\ |\
the first three successive work days - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\
✔✔1, RCMCI ED 6, 3.2.4
|\ |\ |\ |\ |\
Standard specification for loadbearing |\ |\ |\ |\
concrete masonry units - CORRECT ANSWERS ✔✔ASTM C
|\ |\ |\ |\ |\ |\ |\ |\
90 S 2.2.1
|\ |\
Grout admixtures used to obtain high
|\ |\ |\ |\ |\ |\
slump with reduced water - CORRECT ANSWERS ✔✔Super
|\ |\ |\ |\ |\ |\ |\
plasticizer S 2.11.6
|\ |\ |\
Standard specification for autoclaved aerated CMU to
|\ |\ |\ |\ |\ |\ |\
conform to the strength class specified in the documents -
|\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔ASTM C 1386, CI 530 Part 2 S
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
2.3E
Grout used in construction of engineered and empirically
|\ |\ |\ |\ |\ |\ |\ |\
designed masonry structures - CORRECT ANSWERS |\ |\ |\ |\ |\ |\
✔✔ASTM C 476 |\ |\
, accordance for slump test for grout - CORRECT ANSWERS |\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔ASTM C 1019, ASTM C 1019-03 |\ |\ |\ |\ |\
Conditions for grout specimen testing - CORRECT |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Damp, ASTM C 1019-03 |\ |\ |\ |\
How long must prisms cure before being cut according to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
prism test methods - CORRECT ANSWERS ✔✔28 hours,
|\ |\ |\ |\ |\ |\ |\ |\
2006 IBC |\
Min amount of time for masonry prism tests not to be
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
disturbed or moved after construction and grouting -
|\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔48 hours, ASTM C 1314, S 5.10 |\ |\ |\ |\ |\ |\ |\ |\
Amount of time between obtaining first and final portions
|\ |\ |\ |\ |\ |\ |\ |\ |\
of grout when field sampling grout - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔15 minutes, ASTM C 1019, S 7.2.1
|\ |\ |\ |\ |\ |\
Temperature below which glass masonry units shall not |\ |\ |\ |\ |\ |\ |\ |\
be laid - CORRECT ANSWERS ✔✔60 degrees F, 2006 IBC
|\ |\ |\ |\ |\ |\ |\ |\ |\
Min time to cover newly constructed masonry with
|\ |\ |\ |\ |\ |\ |\ |\
weather resistant membrane when temperature is below
|\ |\ |\ |\ |\ |\ |\
40 - CORRECT ANSWERS ✔✔24 hours, 2006 IBC
|\ |\ |\ |\ |\ |\ |\
|\ |\ |\ |\ |\
answers
Number of mortar compression tests taken per day for
|\ |\ |\ |\ |\ |\ |\ |\ |\
the first three successive work days - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\
✔✔1, RCMCI ED 6, 3.2.4
|\ |\ |\ |\ |\
Standard specification for loadbearing |\ |\ |\ |\
concrete masonry units - CORRECT ANSWERS ✔✔ASTM C
|\ |\ |\ |\ |\ |\ |\ |\
90 S 2.2.1
|\ |\
Grout admixtures used to obtain high
|\ |\ |\ |\ |\ |\
slump with reduced water - CORRECT ANSWERS ✔✔Super
|\ |\ |\ |\ |\ |\ |\
plasticizer S 2.11.6
|\ |\ |\
Standard specification for autoclaved aerated CMU to
|\ |\ |\ |\ |\ |\ |\
conform to the strength class specified in the documents -
|\ |\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔ASTM C 1386, CI 530 Part 2 S
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
2.3E
Grout used in construction of engineered and empirically
|\ |\ |\ |\ |\ |\ |\ |\
designed masonry structures - CORRECT ANSWERS |\ |\ |\ |\ |\ |\
✔✔ASTM C 476 |\ |\
, accordance for slump test for grout - CORRECT ANSWERS |\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔ASTM C 1019, ASTM C 1019-03 |\ |\ |\ |\ |\
Conditions for grout specimen testing - CORRECT |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Damp, ASTM C 1019-03 |\ |\ |\ |\
How long must prisms cure before being cut according to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
prism test methods - CORRECT ANSWERS ✔✔28 hours,
|\ |\ |\ |\ |\ |\ |\ |\
2006 IBC |\
Min amount of time for masonry prism tests not to be
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
disturbed or moved after construction and grouting -
|\ |\ |\ |\ |\ |\ |\ |\
CORRECT ANSWERS ✔✔48 hours, ASTM C 1314, S 5.10 |\ |\ |\ |\ |\ |\ |\ |\
Amount of time between obtaining first and final portions
|\ |\ |\ |\ |\ |\ |\ |\ |\
of grout when field sampling grout - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔15 minutes, ASTM C 1019, S 7.2.1
|\ |\ |\ |\ |\ |\
Temperature below which glass masonry units shall not |\ |\ |\ |\ |\ |\ |\ |\
be laid - CORRECT ANSWERS ✔✔60 degrees F, 2006 IBC
|\ |\ |\ |\ |\ |\ |\ |\ |\
Min time to cover newly constructed masonry with
|\ |\ |\ |\ |\ |\ |\ |\
weather resistant membrane when temperature is below
|\ |\ |\ |\ |\ |\ |\
40 - CORRECT ANSWERS ✔✔24 hours, 2006 IBC
|\ |\ |\ |\ |\ |\ |\