Question 2
5 out of 5 points
Which of the following titles in a typical scrum arrangement is the project manager?
Answers:
a.
Scrum developer
b.
Scrum master
c.
Scrum methodologist
d.
Product owner
e.
Scrum leader
,Give this one a try later!
b
Question 14
5 out of 5 points
A project leader's boss has told Jonathan that his project is very important. If the
critical path is delayed, he will be given whatever he needs to get the project back on
schedule. His project is classified as ________ constrained.
Answers:
a.
time
b.
cost
c.
resource
d.
performance
e.
quality
Give this one a try later!
a
Response Feedback: Correct. A time-constrained project is one that must
be completed by an imposed date. If required, resources can be added to
ensure the project is completed by a specific date. Although time is the
critical factor, resource usage should be no more than is necessary and
sufficient.
• Question 12
5 out of 5 points
, Which PMBOK activity is responsible for determining activity resource requirements,
and for determining a resource breakdown structure?
Answers:
a.
Estimate activity resources
b.
Estimate activity durations
c.
Develop schedule
d.
Define activities
e.
Plan schedule management
Give this one a try later!
a
Response Feedback: Correct. The process known as Estimate activity
resources determines resource requirements, and creates a resource
breakdown structure.
Question 19
5 out of 5 points
Seven activities are to be considered for this problem. Additional information about
these activities such as their activity time and immediate predecessors are included in
the table that follows. Use this information to figure out the earliest completion time
for this project using a Gantt chart.
Activity Immediate Predecessor(s) Activity Time(in weeks)
A None 1
B None 1
CA4
DB5
E C, D 5
FE3
GF2
5 out of 5 points
Which of the following titles in a typical scrum arrangement is the project manager?
Answers:
a.
Scrum developer
b.
Scrum master
c.
Scrum methodologist
d.
Product owner
e.
Scrum leader
,Give this one a try later!
b
Question 14
5 out of 5 points
A project leader's boss has told Jonathan that his project is very important. If the
critical path is delayed, he will be given whatever he needs to get the project back on
schedule. His project is classified as ________ constrained.
Answers:
a.
time
b.
cost
c.
resource
d.
performance
e.
quality
Give this one a try later!
a
Response Feedback: Correct. A time-constrained project is one that must
be completed by an imposed date. If required, resources can be added to
ensure the project is completed by a specific date. Although time is the
critical factor, resource usage should be no more than is necessary and
sufficient.
• Question 12
5 out of 5 points
, Which PMBOK activity is responsible for determining activity resource requirements,
and for determining a resource breakdown structure?
Answers:
a.
Estimate activity resources
b.
Estimate activity durations
c.
Develop schedule
d.
Define activities
e.
Plan schedule management
Give this one a try later!
a
Response Feedback: Correct. The process known as Estimate activity
resources determines resource requirements, and creates a resource
breakdown structure.
Question 19
5 out of 5 points
Seven activities are to be considered for this problem. Additional information about
these activities such as their activity time and immediate predecessors are included in
the table that follows. Use this information to figure out the earliest completion time
for this project using a Gantt chart.
Activity Immediate Predecessor(s) Activity Time(in weeks)
A None 1
B None 1
CA4
DB5
E C, D 5
FE3
GF2