PMT 3600V ADVANCED PROGRAM MANAGEMENT EXAM 3

Vista previa del contenido

PMT 3600V ADVANCED PROGRAM
MANAGEMENT EXAM 3



1. Which document establishes the formal link between the Capability Development

Document (CDD) and the Acquisition Strategy?

A. Systems Engineering Plan (SEP)


B. Test and Evaluation Master Plan (TEMP)


C. Life Cycle Sustainment Plan (LCSP)


D. Acquisition Program Baseline (APB)


Answer: D


Conceptual Explanation: The Acquisition Program Baseline (APB) documents the

performance, schedule, and cost goals of a program based on the requirements in the CDD.


2. In the context of Earned Value Management (EVM), if the Cost Performance Index (CPI) is

0.85 and the Schedule Performance Index (SPI) is 1.10, which statement is true?

A. The program is under budget and ahead of schedule.


B. The program is over budget and behind schedule.


C. The program is under budget and behind schedule.


D. The program is over budget and ahead of schedule.

,Answer: D


Conceptual Explanation: A CPI less than 1.0 indicates cost overrun (over budget), while

an SPI greater than 1.0 indicates the program is ahead of schedule.


3. Which contract type places the maximum risk and full responsibility for all costs and

resulting profit or loss upon the contractor?

A. Cost Plus Fixed Fee (CPFF)


B. Fixed Price Incentive Firm (FPIF)


C. Cost Plus Award Fee (CPAF)


D. Firm Fixed Price (FFP)


Answer: D


Conceptual Explanation: Firm Fixed Price contracts place maximum risk on the

contractor as the price is not subject to adjustment based on cost experience.


4. What is the primary purpose of a Technology Readiness Assessment (TRA)?

A. To determine the production readiness of a manufacturer.


B. To validate the operational suitability of a prototype.


C. To assess the cybersecurity vulnerabilities of a system.


D. To evaluate the maturity of Critical Technology Elements (CTEs) before Milestone B.


Answer: D

, Conceptual Explanation: TRAs are conducted to evaluate the maturity of CTEs to ensure

they meet the required Technology Readiness Level (TRL) for milestone decisions.


5. During the Engineering and Manufacturing Development (EMD) phase, which review is

conducted to ensure the design can proceed into fabrication, assembly, and integration?

A. Preliminary Design Review (PDR)


B. Critical Design Review (CDR)


C. System Verification Review (SVR)


D. Production Readiness Review (PRR)


Answer: B


Conceptual Explanation: The Critical Design Review (CDR) assesses design maturity and

determines if the system is ready for fabrication and testing.


6. Which appropriation category is typically used for the modernization and upgrade of

existing major end items?

A. Procurement


B. Operations and Maintenance (O&M)


C. Research, Development, Test, and Evaluation (RDT&E)


D. Military Construction (MILCON)


Answer: A

Información del documento

Subido en
19 de agosto de 2026
Número de páginas
25
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Thebright
3.6
(46)
Vendido
256
Seguidores
6
Artículos
15914
Última venta
6 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes