1. A commercial contractor is preparing a bid for a project where the plans
and specifications contain conflicting requirements. What should the
contractor do first?
A. Use the least expensive requirement
B. Follow whichever document was issued first
C. Request clarification through the designated contract/RFI process
D. Allow the subcontractor to determine the requirement
Rationale: The formal clarification process establishes the controlling
interpretation and creates a documented record before construction proceeds.
2. During excavation for a commercial building, unsuitable soil is discovered
beneath the planned footing elevation. What is the most appropriate
action?
,A. Pour a thicker footing immediately
B. Compact the unsuitable soil without investigation
C. Notify the design professional and obtain an approved remediation approach
D. Continue excavation until the soil appears visually acceptable
Rationale: Unexpected subsurface conditions can affect structural performance
and contract scope, requiring evaluation before proceeding.
3. Which document most directly establishes the contractor's contractual
obligations regarding the quality and execution of construction?
A. Marketing brochure
B. Preliminary estimate
C. Contract documents
D. Contractor's internal schedule
Rationale: The contract documents establish the legal and technical
requirements governing the contractor's work.
4. A contractor discovers that a subcontractor intends to substitute a specified
material without approval. What is the best response?
A. Permit the substitution if it appears equivalent
B. Accept it if the owner does not notice
C. Require the substitution to follow the specified approval procedure
D. Install it and request approval afterward
Rationale: Material substitutions should be formally reviewed and approved
before installation to ensure compliance with design and contractual
requirements.
5. Which scheduling method is particularly useful for identifying activities that
control the overall project completion date?
A. Bar chart only
B. Procurement log
,C. Critical Path Method (CPM)
D. Daily report
Rationale: CPM identifies the sequence of activities that determines the project's
overall duration and completion date.
6. An activity has an early start of day 12 and an early finish of day 18. What is
its duration if the schedule uses the common finish-minus-start
convention?
A. 5 days
B. 6 days
C. 7 days
D. 12 days
Rationale: The duration is calculated as 18 − 12 = 6 days under the stated
convention.
7. A contractor's project schedule shows a critical activity delayed by five
working days with no available float. What is the likely effect?
A. No effect on completion
B. Completion advances five days
C. Project completion is delayed by five working days unless recovery occurs
D. Only procurement is affected
Rationale: A critical activity with zero float directly affects the completion date
when delayed.
8. Which cost category normally includes wages paid to workers directly
performing construction activities?
A. General overhead
B. Financing cost
C. Direct labor
D. Contingency
, Rationale: Labor directly attributable to construction work is a direct project
cost.
9. A contractor estimates direct costs at $850,000 and applies a 12% markup
based on direct cost. What is the markup?
A. $85,000
B. $102,000
C. $112,000
D. $119,000
Rationale: $850,000 × 0.12 = $102,000.
10.Which item is generally considered a project indirect cost rather than a
direct installation cost?
A. Concrete placed in footings
B. Structural steel
C. Drywall installation labor
D. Temporary field office expense
Rationale: Temporary facilities used to administer and support the project are
generally classified as indirect project costs.
11.A commercial contractor is reviewing a subcontractor's pay application.
Which document provides evidence that requested progress payments
correspond to completed work?
A. Contractor's license
B. Schedule of values and supporting documentation
C. Equipment warranty
D. Employee roster
Rationale: The schedule of values allocates the contract amount to measurable
work items and supports progress payment evaluation.
12.What is retainage primarily intended to accomplish?