CDT 2 MOCK TEST WITH ANSWER
RATIONALES 2026
◉ Bid shopping is the practice of:
A) Negotiating with two of more subcontractors for the lowest price
B) Revealing the sub bid of one subcontractor to another to obtain a
lower price
C) Encouraging cost cutting between subcontractors in Value
Analysis
D) Achieving the lowest sub bid for the Owners Benefit..
Answer: B
◉ During project conception, the four major values to be determined
are:
A)
economy, time, insulation, form.
B)
function, economy, time, problem.
C)
time, economy, form, goals.
D)
function, form, economy, time..
,Answer: B
◉ Which of the following will the courts use to interpret
specifications in the same manner as they interpret contracts?
A)
Autonomy to contract
B)
General takes precedence over specific.
C)
Professional negligence
D)
Construction for the drafter.
Answer: A
◉ Submittal requirements for Facility Services Divisions 21 through
28 are specified in:
A)
The first section in each respective division
B)
Supplementary Conditions
C)
Division 01 Section Submittal Procedures
,D)
Section 01 12 00 Summary of Multiple Contracts.
Answer: C
◉ Which of the following is a primary characteristic of Integrated
Project Delivery?
A)
Schematic Design is performed by the Contractor
B)
Recognition that intensified planning results in efficiency and
savings during execution
C)
IPD can only be used with the Design Build delivery method
D)
Reduced efficiency of Project Commissioning.
Answer: B
◉ A detailed description of an Alternate should be located in:
A)
The Bid Form.
B)
Division 01.
, C)
The Agreement.
D)
Sections in Divisions 2-49..
Answer: B
◉ Which of the following groups of Article Headings would occur in
Part 1 of the Three-Part SectionFormat?
A)
Fabrication, quality assurance, and references.
B)
References, submittals, and field quality control.
C)
References, submittals, and quality assurance.
D)
Warranties, allowances, and schedules..
Answer: C
◉ The Contractor should begin preparation and delivery of the
preconstruction submittals after which event?
A)
Bid opening
RATIONALES 2026
◉ Bid shopping is the practice of:
A) Negotiating with two of more subcontractors for the lowest price
B) Revealing the sub bid of one subcontractor to another to obtain a
lower price
C) Encouraging cost cutting between subcontractors in Value
Analysis
D) Achieving the lowest sub bid for the Owners Benefit..
Answer: B
◉ During project conception, the four major values to be determined
are:
A)
economy, time, insulation, form.
B)
function, economy, time, problem.
C)
time, economy, form, goals.
D)
function, form, economy, time..
,Answer: B
◉ Which of the following will the courts use to interpret
specifications in the same manner as they interpret contracts?
A)
Autonomy to contract
B)
General takes precedence over specific.
C)
Professional negligence
D)
Construction for the drafter.
Answer: A
◉ Submittal requirements for Facility Services Divisions 21 through
28 are specified in:
A)
The first section in each respective division
B)
Supplementary Conditions
C)
Division 01 Section Submittal Procedures
,D)
Section 01 12 00 Summary of Multiple Contracts.
Answer: C
◉ Which of the following is a primary characteristic of Integrated
Project Delivery?
A)
Schematic Design is performed by the Contractor
B)
Recognition that intensified planning results in efficiency and
savings during execution
C)
IPD can only be used with the Design Build delivery method
D)
Reduced efficiency of Project Commissioning.
Answer: B
◉ A detailed description of an Alternate should be located in:
A)
The Bid Form.
B)
Division 01.
, C)
The Agreement.
D)
Sections in Divisions 2-49..
Answer: B
◉ Which of the following groups of Article Headings would occur in
Part 1 of the Three-Part SectionFormat?
A)
Fabrication, quality assurance, and references.
B)
References, submittals, and field quality control.
C)
References, submittals, and quality assurance.
D)
Warranties, allowances, and schedules..
Answer: C
◉ The Contractor should begin preparation and delivery of the
preconstruction submittals after which event?
A)
Bid opening