P 99 test
Study online at https://quizlet.com/_3wu1or
1. All heating combustion and cooking equipment shall Where clearances are ad-
be installed equate from combustible
construction
2. If the equipment is not insulated the building con- 170 Degrees
struction shall be fire protected so that the surface of
combustible construction materials will not be raised
to a temperature higher than
3. Boilers shall be operated upon completion of construc- False
tion
4. How often must the boilers and chimney connections New installations every six
be inspected months
5. And annual written statement by the building owner Commissioner
specifying the location and inspection arrangement
shall be filled with who
6. All fuel oil piping and fuel oil storage tanks shall be Hydrostatic test
given what type of test for tightness
7. Who performs the test The contractor who made
the installation
8. The piping shall be pressure tested so what maximum 1 1/2 times the working
working pressure of the piping pressure
9. The minimum pressure for testing the tightness of the 1 1/2 the maximum work-
storage tank Shelby ing pressure applicable to
the tank
10. False
1/9
, P 99 test
Study online at https://quizlet.com/_3wu1or
The hydrostatic pressure shall be maintained until all
joints and connections have been visually inspected
for leaks but for no less than 15 minutes
11. Instruction cards for oil burning equipment shall be False
furnished and be permanently located in accessible in
the building owners office
12. No oil burning equipment shall be operated until the True
requirements of the air pollution control code have
been met
13. No oil burning equipment shall be operated until the True
approval for the storage of your oil has been approved
by the fire commissioner
14. If the oil burning installation is not fully automatic or False
requires preheating a person holding a certificate of
fitness is not required
15. The certificate holder shall be present in the building False
only on the start of the boiler operation
16. Wisen's or qualified operators are required to All of the above
17. Low temperature equipment is designated as Who's temperature of
combustion products at
the point of equipment
exit is 600°F or less un-
der normal operating con-
ditions
18. The amount of ventilation air required for each gallon 36 CFM
of oil per our shall be no less than
2/9
Study online at https://quizlet.com/_3wu1or
1. All heating combustion and cooking equipment shall Where clearances are ad-
be installed equate from combustible
construction
2. If the equipment is not insulated the building con- 170 Degrees
struction shall be fire protected so that the surface of
combustible construction materials will not be raised
to a temperature higher than
3. Boilers shall be operated upon completion of construc- False
tion
4. How often must the boilers and chimney connections New installations every six
be inspected months
5. And annual written statement by the building owner Commissioner
specifying the location and inspection arrangement
shall be filled with who
6. All fuel oil piping and fuel oil storage tanks shall be Hydrostatic test
given what type of test for tightness
7. Who performs the test The contractor who made
the installation
8. The piping shall be pressure tested so what maximum 1 1/2 times the working
working pressure of the piping pressure
9. The minimum pressure for testing the tightness of the 1 1/2 the maximum work-
storage tank Shelby ing pressure applicable to
the tank
10. False
1/9
, P 99 test
Study online at https://quizlet.com/_3wu1or
The hydrostatic pressure shall be maintained until all
joints and connections have been visually inspected
for leaks but for no less than 15 minutes
11. Instruction cards for oil burning equipment shall be False
furnished and be permanently located in accessible in
the building owners office
12. No oil burning equipment shall be operated until the True
requirements of the air pollution control code have
been met
13. No oil burning equipment shall be operated until the True
approval for the storage of your oil has been approved
by the fire commissioner
14. If the oil burning installation is not fully automatic or False
requires preheating a person holding a certificate of
fitness is not required
15. The certificate holder shall be present in the building False
only on the start of the boiler operation
16. Wisen's or qualified operators are required to All of the above
17. Low temperature equipment is designated as Who's temperature of
combustion products at
the point of equipment
exit is 600°F or less un-
der normal operating con-
ditions
18. The amount of ventilation air required for each gallon 36 CFM
of oil per our shall be no less than
2/9