AZ ROC TRADE EXAM SCRIPT TESTED
QUESTIONS FULL SOLUTION PREMIUM
STUDY MATERIAL
●● Can a license be transferred, assigned or Lease to another person or
entity?
Answer: No
●● What financial security is required before a license can be issued?
Answer: A surety bond or cash deposit with the ROC to protect the
public and supplier against financial loss
●● How soon must the contractor notify the ROC of a change in
qualifying party?
Answer: Failure to report a new qualifying party within 15 days is a
violation
●● If customer wants to file a complaint with the ROC, the residential
contractor must
Answer: Contractors must inform customers in writing about how to file
a complaint with the ROC before starting the work.
, ●● What's the penalty for a contractor who does not pay court ordered
restitution to a consumer?
Answer: The contractor's license may be suspended or revoked
●● What must a (residential) contractor do before filing a lawsuit to
collect payment?
Answer: Serve a 20 day written preliminary notice
●● Who can act as a qualifying party for a contracting business?
Answer: An owner, officer, member, or employee with the necessary
experience and skill
●● True or false?
If there is an urgent threat, the ROC could suspend a license before a
formal hearing
Answer: True
●● Within how many days must a contractor response to a written
complaint from the ROC?
Answer: Within 20 days
●● What must happen before a contractor could perform work over
$1000 on the property?
Answer: A written contract must be signed by both parties
QUESTIONS FULL SOLUTION PREMIUM
STUDY MATERIAL
●● Can a license be transferred, assigned or Lease to another person or
entity?
Answer: No
●● What financial security is required before a license can be issued?
Answer: A surety bond or cash deposit with the ROC to protect the
public and supplier against financial loss
●● How soon must the contractor notify the ROC of a change in
qualifying party?
Answer: Failure to report a new qualifying party within 15 days is a
violation
●● If customer wants to file a complaint with the ROC, the residential
contractor must
Answer: Contractors must inform customers in writing about how to file
a complaint with the ROC before starting the work.
, ●● What's the penalty for a contractor who does not pay court ordered
restitution to a consumer?
Answer: The contractor's license may be suspended or revoked
●● What must a (residential) contractor do before filing a lawsuit to
collect payment?
Answer: Serve a 20 day written preliminary notice
●● Who can act as a qualifying party for a contracting business?
Answer: An owner, officer, member, or employee with the necessary
experience and skill
●● True or false?
If there is an urgent threat, the ROC could suspend a license before a
formal hearing
Answer: True
●● Within how many days must a contractor response to a written
complaint from the ROC?
Answer: Within 20 days
●● What must happen before a contractor could perform work over
$1000 on the property?
Answer: A written contract must be signed by both parties