WGU E012 Task 2| Enterprise Digital Transformation Implementation & Execution Plan | 2026 Update
with complete solutions.
This implementation plan continues the project established in Task 1: a 28-week, $850,000
enterprise digital transformation using predictive controls for procurement and infrastructure and
Agile Scrum for software configuration, integration, migration, and testing. Verify all details
against the official WGU case and rubric before submitting.
Executive Summary
All-In-One Enterprise will implement an integrated cloud-enabled enterprise platform to replace
fragmented legacy applications, manual workflows, inconsistent security controls, and unreliable
reporting processes. Task 1 established the business case, scope, governance structure, hybrid
methodology, preliminary budget, and project charter. This implementation and execution plan
defines how the approved solution will be deployed, tested, migrated, governed, and transitioned
into normal operations.
The 28-week implementation is organized into six chronological phases: mobilization and
procurement, cloud landing-zone and infrastructure configuration, iterative platform
configuration, data migration and pilot deployment, enterprise testing and production readiness,
and final deployment and stabilization. Predictive controls will govern architecture, purchasing,
contracts, milestone gates, and production authorization. Two-week Agile Scrum sprints will
support application configuration, integration development, migration refinement, dashboards,
user testing, and defect correction.
The implementation will use formal dependencies and stage gates to prevent technical work from
advancing before its prerequisites are complete. The critical path runs from requirements and
architecture approval through procurement, cloud configuration, platform configuration,
migration rehearsal, user-acceptance testing, final migration, production cutover, and operational
acceptance.
Data will be profiled, classified, mapped, cleansed, deduplicated, encrypted, migrated,
reconciled, and approved by accountable data owners. The quality plan includes unit, system,
integration, regression, performance, recovery, security, and user-acceptance testing. If
predefined go-live conditions are not met, the project will execute a controlled rollback that
restores the legacy environment without losing transactions completed during the deployment
window.
A. Comprehensive Implementation Schedule
and Sequencing
,A1. Phase-by-Phase Scheduling
The implementation timeline for the proposed IT solution is divided into six chronological
phases completed over 28 weeks. Some activities overlap when dependencies permit, but no
workstream may pass its stage gate without documented approval.
Phase 1: Mobilization, Discovery, and Procurement
Weeks 1–6
The purpose of Phase 1 is to confirm requirements, mobilize resources, establish governance,
and initiate the acquisition of long-lead technology components.
Major activities
Confirm the approved project charter and funding
Conduct the project kickoff
Establish the steering committee and workstream teams
Validate business, technical, security, and data requirements
Inventory applications, integrations, infrastructure, and data sources
Complete current-state performance baselines
Finalize the target architecture
Complete the security and privacy impact assessment
Develop the procurement package
Evaluate vendors and negotiate contracts
Order approved hardware and software licenses
Establish the product backlog
Establish risk, issue, decision, and change registers
Deliverables
Approved requirements baseline
Approved target architecture
Approved security design
Application and data inventory
Vendor contracts
Procurement schedule
Prioritized product backlog
Integrated implementation schedule
Baseline performance measurements
Exit criteria
Phase 1 will be complete when:
, The sponsor approves the requirements baseline.
The enterprise architect approves the target architecture.
The CISO approves the security requirements.
Vendors and contracts are approved.
Required hardware and licenses are ordered.
Workstream resources are formally assigned.
Phase 2: Infrastructure and Cloud Landing-Zone
Configuration
Weeks 7–12
Phase 2 establishes the secured technical foundation required for platform configuration,
integration, testing, and data migration.
Major activities
Receive and inspect purchased equipment
Configure development, testing, staging, and production subscriptions
Establish network connectivity and segmentation
Configure firewalls, virtual networks, routing, and private endpoints
Configure identity federation and single sign-on
Implement multifactor authentication
Establish role-based access-control groups
Configure encryption and key-management services
Configure centralized logging and security monitoring
Establish backup policies
Configure development and testing environments
Validate infrastructure performance and security
Conduct a landing-zone readiness review
Deliverables
Secured cloud landing zone
Configured network and security infrastructure
Identity and access-management configuration
Development, test, staging, and production environments
Backup and monitoring services
Infrastructure operating procedures
Landing-zone validation report
Exit criteria
with complete solutions.
This implementation plan continues the project established in Task 1: a 28-week, $850,000
enterprise digital transformation using predictive controls for procurement and infrastructure and
Agile Scrum for software configuration, integration, migration, and testing. Verify all details
against the official WGU case and rubric before submitting.
Executive Summary
All-In-One Enterprise will implement an integrated cloud-enabled enterprise platform to replace
fragmented legacy applications, manual workflows, inconsistent security controls, and unreliable
reporting processes. Task 1 established the business case, scope, governance structure, hybrid
methodology, preliminary budget, and project charter. This implementation and execution plan
defines how the approved solution will be deployed, tested, migrated, governed, and transitioned
into normal operations.
The 28-week implementation is organized into six chronological phases: mobilization and
procurement, cloud landing-zone and infrastructure configuration, iterative platform
configuration, data migration and pilot deployment, enterprise testing and production readiness,
and final deployment and stabilization. Predictive controls will govern architecture, purchasing,
contracts, milestone gates, and production authorization. Two-week Agile Scrum sprints will
support application configuration, integration development, migration refinement, dashboards,
user testing, and defect correction.
The implementation will use formal dependencies and stage gates to prevent technical work from
advancing before its prerequisites are complete. The critical path runs from requirements and
architecture approval through procurement, cloud configuration, platform configuration,
migration rehearsal, user-acceptance testing, final migration, production cutover, and operational
acceptance.
Data will be profiled, classified, mapped, cleansed, deduplicated, encrypted, migrated,
reconciled, and approved by accountable data owners. The quality plan includes unit, system,
integration, regression, performance, recovery, security, and user-acceptance testing. If
predefined go-live conditions are not met, the project will execute a controlled rollback that
restores the legacy environment without losing transactions completed during the deployment
window.
A. Comprehensive Implementation Schedule
and Sequencing
,A1. Phase-by-Phase Scheduling
The implementation timeline for the proposed IT solution is divided into six chronological
phases completed over 28 weeks. Some activities overlap when dependencies permit, but no
workstream may pass its stage gate without documented approval.
Phase 1: Mobilization, Discovery, and Procurement
Weeks 1–6
The purpose of Phase 1 is to confirm requirements, mobilize resources, establish governance,
and initiate the acquisition of long-lead technology components.
Major activities
Confirm the approved project charter and funding
Conduct the project kickoff
Establish the steering committee and workstream teams
Validate business, technical, security, and data requirements
Inventory applications, integrations, infrastructure, and data sources
Complete current-state performance baselines
Finalize the target architecture
Complete the security and privacy impact assessment
Develop the procurement package
Evaluate vendors and negotiate contracts
Order approved hardware and software licenses
Establish the product backlog
Establish risk, issue, decision, and change registers
Deliverables
Approved requirements baseline
Approved target architecture
Approved security design
Application and data inventory
Vendor contracts
Procurement schedule
Prioritized product backlog
Integrated implementation schedule
Baseline performance measurements
Exit criteria
Phase 1 will be complete when:
, The sponsor approves the requirements baseline.
The enterprise architect approves the target architecture.
The CISO approves the security requirements.
Vendors and contracts are approved.
Required hardware and licenses are ordered.
Workstream resources are formally assigned.
Phase 2: Infrastructure and Cloud Landing-Zone
Configuration
Weeks 7–12
Phase 2 establishes the secured technical foundation required for platform configuration,
integration, testing, and data migration.
Major activities
Receive and inspect purchased equipment
Configure development, testing, staging, and production subscriptions
Establish network connectivity and segmentation
Configure firewalls, virtual networks, routing, and private endpoints
Configure identity federation and single sign-on
Implement multifactor authentication
Establish role-based access-control groups
Configure encryption and key-management services
Configure centralized logging and security monitoring
Establish backup policies
Configure development and testing environments
Validate infrastructure performance and security
Conduct a landing-zone readiness review
Deliverables
Secured cloud landing zone
Configured network and security infrastructure
Identity and access-management configuration
Development, test, staging, and production environments
Backup and monitoring services
Infrastructure operating procedures
Landing-zone validation report
Exit criteria