WGU E012 Task 2| Enterprise Digital Transformation Implementation & Execution Plan | 2026 Update with complete solutions.

Document preview thumbnail
Vista previa 3 fuera de 28 páginas

WGU E012 Task 2| Enterprise Digital Transformation Implementation & Execution Plan | 2026 Update with complete solutions.

Vista previa del contenido

WGU E012 Task 2| Enterprise Digital Transformation Implementation & Execution Plan | 2026 Update
with complete solutions.

This implementation plan continues the project established in Task 1: a 28-week, $850,000
enterprise digital transformation using predictive controls for procurement and infrastructure and
Agile Scrum for software configuration, integration, migration, and testing. Verify all details
against the official WGU case and rubric before submitting.




Executive Summary
All-In-One Enterprise will implement an integrated cloud-enabled enterprise platform to replace
fragmented legacy applications, manual workflows, inconsistent security controls, and unreliable
reporting processes. Task 1 established the business case, scope, governance structure, hybrid
methodology, preliminary budget, and project charter. This implementation and execution plan
defines how the approved solution will be deployed, tested, migrated, governed, and transitioned
into normal operations.

The 28-week implementation is organized into six chronological phases: mobilization and
procurement, cloud landing-zone and infrastructure configuration, iterative platform
configuration, data migration and pilot deployment, enterprise testing and production readiness,
and final deployment and stabilization. Predictive controls will govern architecture, purchasing,
contracts, milestone gates, and production authorization. Two-week Agile Scrum sprints will
support application configuration, integration development, migration refinement, dashboards,
user testing, and defect correction.

The implementation will use formal dependencies and stage gates to prevent technical work from
advancing before its prerequisites are complete. The critical path runs from requirements and
architecture approval through procurement, cloud configuration, platform configuration,
migration rehearsal, user-acceptance testing, final migration, production cutover, and operational
acceptance.

Data will be profiled, classified, mapped, cleansed, deduplicated, encrypted, migrated,
reconciled, and approved by accountable data owners. The quality plan includes unit, system,
integration, regression, performance, recovery, security, and user-acceptance testing. If
predefined go-live conditions are not met, the project will execute a controlled rollback that
restores the legacy environment without losing transactions completed during the deployment
window.




A. Comprehensive Implementation Schedule
and Sequencing

,A1. Phase-by-Phase Scheduling
The implementation timeline for the proposed IT solution is divided into six chronological
phases completed over 28 weeks. Some activities overlap when dependencies permit, but no
workstream may pass its stage gate without documented approval.

Phase 1: Mobilization, Discovery, and Procurement
Weeks 1–6

The purpose of Phase 1 is to confirm requirements, mobilize resources, establish governance,
and initiate the acquisition of long-lead technology components.

Major activities

 Confirm the approved project charter and funding
 Conduct the project kickoff
 Establish the steering committee and workstream teams
 Validate business, technical, security, and data requirements
 Inventory applications, integrations, infrastructure, and data sources
 Complete current-state performance baselines
 Finalize the target architecture
 Complete the security and privacy impact assessment
 Develop the procurement package
 Evaluate vendors and negotiate contracts
 Order approved hardware and software licenses
 Establish the product backlog
 Establish risk, issue, decision, and change registers

Deliverables

 Approved requirements baseline
 Approved target architecture
 Approved security design
 Application and data inventory
 Vendor contracts
 Procurement schedule
 Prioritized product backlog
 Integrated implementation schedule
 Baseline performance measurements

Exit criteria

Phase 1 will be complete when:

,  The sponsor approves the requirements baseline.
 The enterprise architect approves the target architecture.
 The CISO approves the security requirements.
 Vendors and contracts are approved.
 Required hardware and licenses are ordered.
 Workstream resources are formally assigned.




Phase 2: Infrastructure and Cloud Landing-Zone
Configuration
Weeks 7–12

Phase 2 establishes the secured technical foundation required for platform configuration,
integration, testing, and data migration.

Major activities

 Receive and inspect purchased equipment
 Configure development, testing, staging, and production subscriptions
 Establish network connectivity and segmentation
 Configure firewalls, virtual networks, routing, and private endpoints
 Configure identity federation and single sign-on
 Implement multifactor authentication
 Establish role-based access-control groups
 Configure encryption and key-management services
 Configure centralized logging and security monitoring
 Establish backup policies
 Configure development and testing environments
 Validate infrastructure performance and security
 Conduct a landing-zone readiness review

Deliverables

 Secured cloud landing zone
 Configured network and security infrastructure
 Identity and access-management configuration
 Development, test, staging, and production environments
 Backup and monitoring services
 Infrastructure operating procedures
 Landing-zone validation report

Exit criteria

Información del documento

Subido en
1 de agosto de 2026
Número de páginas
28
Escrito en
2026/2027
Tipo
Otro
Personaje
Desconocido
$17.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Wiseman
3.9
(1703)
Vendido
8786
Seguidores
3921
Artículos
32303
Última venta
3 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes