PJM DESIGNER HACKS EXAM QUESTIONS AND VERIFIED ANSWERS

Document preview thumbnail
Vista previa 3 fuera de 16 páginas

PJM DESIGNER HACKS EXAM QUESTIONS AND VERIFIED ANSWERS

Vista previa del contenido

What are possible advantages for a cost-plus-fee method of compensation in an
owner-contractor relationship? Check the two that apply.


A. Ensures more competitive bids
B. The cost is known at the outset
C. Allows the construction to start before the design is completed
D. Less risky for the client
E. More flexibility in compensation


Give this one a try later!


CE




The Civil Rights Act, Title VII prohibits discrimination against which of the following?
Check any that apply.


A. Race

,B. Disability
C. Age
D. Political affiliation
E. Color


Give this one a try later!


AE

Employers with 15+ employees comply with the Civil Rights Act, Title VII
which prohibits discrimination against:


Race
Color
National origin
Religion
Gender
Sexual orientation
Discrimination against disability is covered by the Americans with
Disabilities Act (ADA) for employers with 15+ employees.
Discrimination against age is covered by the Age Discrimination in
Employment Act (ADEA) for employers with 20+ employees.




What is the total working fee?


A. The business' percent profit that is built-in to all billable hours
B. The billing rate multiplied by the total time spent for each team member
C. The fee left to pay participants of a team after profits, consultant's fees and other
expenses are deducted
D. The total cost to pay employees and team members
E. The total fee given for all work


Give this one a try later!


C

, Work plans are used as a tool in project management. Which of the following
statements regarding this tool are true? Check the three that apply.


A. Creating a work plan is one of the most important tasks that should be done as
early as possible
B. A work plan is sometimes referred to as a fee proposal
C. A work plan is sometimes referred to as a fee projection
D. Must be detailed enough to assign tasks to individual staff members
E. The first task of a work plan is at the bottom of the schedule


Give this one a try later!


ADE


"The work plan is a document that [firms] use to organize a project. It
outlines the plan by which the company plans to complete a quality project
within a given amount of time and in compliance with a set budget." via
Colorado.edu

For more information on work plans reference The Architect's Handbook of
Professional Practice p. 586




Prior to the partial occupancy of a project still undergoing construction which parties
should inspect the area to be occupied? Check any that apply.


A. Owner
B. Surety
C. Architect
D. Building Inspector
E. Contractor
F. Contractor's General Liability Insurance Company


Give this one a try later!

Información del documento

Subido en
28 de julio de 2026
Número de páginas
16
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$10.50

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
BestKey
4.3
(116)
Vendido
278
Seguidores
108
Artículos
8363
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes