,Which role is responsible for identifying existing and A
predictable hazards and has the authority to correct
them?
A. Authorized Person
B. Competent Person
C. Qualified Person
D. Installer
A "qualified person" is best described as: C
A. Anyone trained by employer
B. One who can supervise work
C. One with recognized degree/cert/experience to solve
problems
D. Any foreman
Ref: OSHA 1926.32(m)
Which document is most directly used to control work B
steps and hazards for a specific task?
A. RF plot
B. JHA/JSA
C. Invoice
D. As-built Ref: OSHA safety planning concepts
When must a rescue plan be in place? B
A. After First Climb
B. Before Work Begins
C. Only if >200ft
D. Only if a hoist is used
Ref: ANSI Z359 (rescue) + OSHA Expectations
Which is the best order for hazard controls? C
A. PPE->Engineering->Admin
B. Engineering->PPE->Elimination
C. Elimination->Substitution->Engineering-
>Administrative->PPE
D. Administrative->PPE->Elimination
Ref: OSHA Hazard Control Hierarchy (General Safety
Doctrine)
Who must verify component compatibility in a fall arrest B
system?
A. Any climber
B. Qualified Person/Competent Person per Plan
C. Customer
D. Safety Observer only
Ref: ANSI Z359 Guidance + NWSA Planning Items
What's the best definition of "Fall Restraint?" B
A. Stops fall after it happens
B. Prevents reaching fall hazard
C. Uses Deceleration Device
D. Requires Rescue System
Ref: ANSI Z359 Fall Protection Code
What is the primary purpose of a pre-task plan ("PTP")? B
A. Billing
B. Identify Hazards + Define Controls + Roles
C. Determine RF License
D. Choose Paint Color
Ref: ANSI/ASSP A10-Series Planning
, An "Authorized Person" is typically: B
A. Engineer
B. Person Approved to perform duties requiring
protection
C. OSHA Inspector
D. Tower Owner
Ref: ANSI Z359 Definitions
Which is a leading indicator? B
A. Recordable Rate
B. Near-Miss Reporting
C. Workers' Comp Costs
D. Fatality Count
Ref: ASSP A10 Program Concepts
A "Stop Work" Authority Should Be: C
A. Limited to Management
B. Limited to Safety Director
C. Available to ALL Workers
D. Only for RF Hazards
Ref: A10 Safety Practice Expectations; NSWA Ref. Set.
When weather changes (Gusts, Lightning, etc.), the C
correction action is to:
A. Finish Quickly
B. Continue if behind schedule
C. Reassess Hazards and Suspend as Needed
D. Only Notify Customer
Ref: A10.48 Safe Work Practices Concept
If a procedure conflicts with a manufacturer instruction, B
you should follow:
A. The cheapest option
B. The Manufacturer Instruction (unless engineered
alternative approved)
C. The Newest Employee
D. None of the Above
Ref: A10.48 + ANSI Z359 Manufacturer Instructions
Emphasis
What is the purpose of a tailored(tailgate)/"toolbox" talk? B
A. Payroll
B. Verify Hazards, Controls & Task Sequencing
C. RF Exposure Mapping
D. FAA Notice Filing
REF: A10 Safety Practice Expectations
Which is most likely a "Critical Lift?" B
A. Hand-Carry Tools
B. Hoisting a large antenna over active antenna lines
C. Climbing 20 ft
D. Sweeping Coax
Ref: A10.48 Rigging/Hoisting Planning Concepts + B30
Series Awareness
A crew member reports damaged gear. The correct B
action to take is:
A. Tape it
B. Remove it from service pending evaluation
C. Use only at low height
D. Let Customer Decide
Ref: ANSI Z359 Inspection Rules