Examen

Virginia Contractors A & B License Study Guide and Licensing Review

Document preview thumbnail
Vista previa 2 fuera de 10 páginas

Comprehensive study guide covering Virginia contractor licensing requirements, construction law, business management, estimating, project management, safety regulations, contracts, building codes, financial management, and risk management. Ideal for contractors preparing for Virginia Class A and Class B licensing examinations.

Vista previa del contenido

VIRGINIA CONTRACTORS STUDY GUIDE 2026
A&B LICENSE | QUESTIONS AND 100% VERIFIED
ANSWERS | GRADED A+ | GUARANTEED PASS!!

A contractor does not notify a change of address and so does not receive a timely
Notice of Renewal. Who is responsible when the contractor does not renew his
license on time?

a. USBC
b. OSHA
c. The licensee Contractor
d. DPOR
- answer-c. The licensee Contractor

A contractor is required to submit a renewal within days of the expiration
date?

a. 20
b. 30
c. 50
d. 180
- answer-b. 30

A designated employee should be?

a. a full time worker
b. at least 18 years old, full time employee, has passed required examination
c. at least 18 years old and 5 years experienced for class A
d. the owner
- answer-b. at least 18 years old, full time employee, has passed required
examination

An erosion control conservation plan needs to be approved within days.

a. 18 days
b. 60 days
c. 29 days

, d. 45 days
- answer-d. 45 days

If a contract awards more than $ per payment, the contractor is required
to have a Class A.

a. 120,000
b. 7,500
c. 750,000
d. 150,000
- answer-a. 120,000

If a contractor earns more than $ per year, than the contractor is required
a Class A license.

a. 120,000
b. 7,500
c. 750,000
d. 150,000
- answer-c. 750,000
A company has 10,000$ in current assets, 100,000 of long term assets, 50,000 of
current liabilities, and 40,000 of long term liabilities. The maximum bond of single
product for this company would typically be limited to

a. 10,000
b. 50,000
c. 100,000
d. 500,000
- answer-d. 500,000

A contract calls for liquidated damage of 500$ per day. The project completed five
days late because it was delayed by rain. The completion would have been 10 days
earlier if it were not for the rain delay. There was a 500$ bonus per day for the
contractor early completion. No extension of time was requested or granted. How
much does the contractor earn or owe?

a. owes 2,500 in liquidated damage
b. owes 500 in liquidated damage
c. is due a 2,500 bonus from the owner

Información del documento

Subido en
25 de julio de 2026
Número de páginas
10
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$13.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
mindvault
5.0
(6)
Vendido
32
Seguidores
1
Artículos
1705
Última venta
3 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes