PMI-Project Management Professional
(PMP) Exam Questions and Correct Answers
Question 1
Which type of analysis is used as a general management technique within the Plan
Procurements process?
A. Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis
Correct Answer
B
Question 2
A tool and technique used during the Perform Qualitative Risk Analysis process is:
A. risk data quality assessment.
B. variance and trend analysis.
C. data gathering and representation techniques.
D. risk audits.
Correct Answer
A
Page 1 of 456
,Question 3
Which of the following types of a dependency determination is used to define the
sequence of activities?
A. Legal
B. Discretionary
C. Internal
D. Resource
Correct Answer
B
Question 4
Which of the following is an input to Direct and Manage Project Execution?
A. Performance reports
B. Project charter
C. Outputs from planning processes
D. Enterprise environmental factors
Correct Answer
D
Page 2 of 456
,Question 5
In the Plan Procurement Management process, which source selection criteria
analyzes if the seller's proposed technical methodologies, techniques, solutions, and
services meet the procurement documents requirements?
A. Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest
Correct Answer
A
Question 6
A project manager is appointed full-time to a project and is given full-time
administrative staff and full-time project team members. This situation describes
which type of organizational structure?
A. Projectized
B. Weak matrix
C. Functional
D. Balanced matrix
Correct Answer
A
Page 3 of 456
, Question 7
Which of the following processes are part of the Project Integration Management
Knowledge Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or
Phase
Correct Answer
D
Question 8
When is a Salience Model used?
A. In a work breakdown structure (WBS)
B. During quality assurance
C. In stakeholder analysis
D. During quality control (QC)
Correct Answer
C
Page 4 of 456
(PMP) Exam Questions and Correct Answers
Question 1
Which type of analysis is used as a general management technique within the Plan
Procurements process?
A. Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis
Correct Answer
B
Question 2
A tool and technique used during the Perform Qualitative Risk Analysis process is:
A. risk data quality assessment.
B. variance and trend analysis.
C. data gathering and representation techniques.
D. risk audits.
Correct Answer
A
Page 1 of 456
,Question 3
Which of the following types of a dependency determination is used to define the
sequence of activities?
A. Legal
B. Discretionary
C. Internal
D. Resource
Correct Answer
B
Question 4
Which of the following is an input to Direct and Manage Project Execution?
A. Performance reports
B. Project charter
C. Outputs from planning processes
D. Enterprise environmental factors
Correct Answer
D
Page 2 of 456
,Question 5
In the Plan Procurement Management process, which source selection criteria
analyzes if the seller's proposed technical methodologies, techniques, solutions, and
services meet the procurement documents requirements?
A. Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest
Correct Answer
A
Question 6
A project manager is appointed full-time to a project and is given full-time
administrative staff and full-time project team members. This situation describes
which type of organizational structure?
A. Projectized
B. Weak matrix
C. Functional
D. Balanced matrix
Correct Answer
A
Page 3 of 456
, Question 7
Which of the following processes are part of the Project Integration Management
Knowledge Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or
Phase
Correct Answer
D
Question 8
When is a Salience Model used?
A. In a work breakdown structure (WBS)
B. During quality assurance
C. In stakeholder analysis
D. During quality control (QC)
Correct Answer
C
Page 4 of 456