◉ An emergency vaccine roll-out project should be deployed to
vaccination centers as soon as confirmed locations are booked.
Factors such as delayed batch shipments, safety protocols, and
target age groups may block the deployment at the last minute.
However, the deployment process does NOT vary after passing the
tollgate to begin setup at a new location.Which project approach
would best support the goal of maximizing the number of centers
deployed?
Answer: A set of predictive deployment sequences embedded in a
set of agile processes.
◉ Early in the establishment of the project, the project manager
spends time looking for historical data that might be helpful in
planning the new project. She is looking for examples of project
documents in similar projects that have been completed that she
might be able to use as templates for the new project. She is also
looking for information about established processes and procedures
that will help the project run more smoothly.What is the term used
to define these?
Answer: OPAs
,◉ A project manager experienced in predictive methods is taking on
an agile project for the first time. To help in making a successful
transition, the project manager makes a list of situations that may
arise from inadequate action as a servant leader.Which three
situations would be on this list? (Choose THREE.)
Answer: A. Team members avoid taking on challenging tasks.
B. Team members avoid direct communication with other
departments.
E. Project stakeholders' express skepticism of agile methods.
◉ On an agile project, minor impediments may interfere with or
slow down day-to-day progress. Which tool or practice can be used
to bring attention to those impediments on a regular basis?
Answer: Daily standups
◉ A company executive who is not a key project stakeholder of a
project has expressed continued interest and opinions directly to the
project team. The key stakeholders are becoming annoyed and
perceive the executive to be interfering and causing unwanted noise,
but the project team finds the executive's inputs helpful.What should
the team do first?
Answer: Discuss what should happen at the next retrospective.
◉ A company is using a predictive approach for the development of
a particular component as defined in the scope management plan.
,Due to regularly changing regulatory requirements, the
development team has requested to utilize agile approaches.What
should the project manager do about the development team's
request?
Answer: Analyze the requirements that will need to be addressed
under the requested method
◉ A project manager implemented an approved change to manage a
risk. Three (3) months after the implemented change, the project
manager learns that the change did NOT produce the desired result,
instead producing negative consequences.How can the project
manager avoid this problem in future projects?
Answer: Update the list on the risk register with the risk.
◉ A project manager is an aggressive project manager known for
producing results. The project manager aims to pick an
organizational structure where the authority of the project manager
is the highest.What organizational structure should the project
manager request from the sponsor?
Answer: Projectized
◉ A Canadian start-up company announces to the press its
imminent launch in the European Union (EU) and Latin America.
Soon afterward, the compliance team recommends delaying the
launch by 6 months to avoid substantial penalties related to a new
set of EU regulations.Which approach could the project manager
, take to advance the launch project while preparing the compliance
measures?
Answer: Split work affected by the regulations into an agile track
and replan unaffected work in the predictive schedule.
◉ A project's daily standup meetings are long, often lasting more
than two hours. The project team uses the standup meetings for
extended discussions about solutions to project obstacles.What
should the project manager do to improve the daily standup
meetings?
Answer: Coach team members towards shortening standup
meetings to 10-15 minutes and improve their method for identifying
solutions.
◉ Before the next iteration begins, project team B meets about an
unexpected challenge that threatens to delay the current phase. The
task in the next iteration CANNOT be completed because of this
challenge. Another team within the project depends on the timely
completion of Task 1 in order to fulfill their work. How should the
project manager resolve this issue?
Answer: Meet with the product owner to prioritize the iteration
backlog, so that it does NOT impact other teams or obligations.
◉ There has been a major change in the company's direction due to
management change and the realignment of long-term goals. 30% of
the staff from the project have been asked to leave. The remaining