A _________ describes the present state of the project and provides compares
the project's actual progress to the baseline plan.
a. Budget report
b. Status report
c. Progress report
d. Forecast report

e. News report - ✔✔b


Schedule Variance (SV) is __________
a. how much time it took to complete the work
b. how long we expected the task to take
c. how much time we have left to complete the project
d. how much time it should have taken to complete the task

e. the difference between the current progress and the original schedule - ✔✔e


The budgeted cost of work scheduled for an activity or component of the WBS is
the _____.
a. Planned Value (PV)
b. Budget At Completion (BAC)
c. Actual Cost (AC)
d. Expected Time Complete (ETC)

e. Estimate at Completion (EAC) - ✔✔a

,A cost variance (CV) can be positive or negative, but never zero. - ✔✔false


Which of the following is not likely a characteristic of a good project metric?:
a. Understandable
b. Quantifiable
c. Cost Effective
d. Subjective

e. High Impact - ✔✔d


A metric that provides an estimate for completing the scheduled work that
remains once the project is started is called the:
a. Planned Value (PV)
b. Budget At Completion (BAC)
c. Actual Cost (AC)
d. Expected Time Complete (ETC)

e. Estimate at Completion (EAC) - ✔✔d


Actual Cost (AC) is __________
a. how much we actually spent for work completed
b. how much we budgeted to spend at the beginning of the project
c. how much of the budget we have left to spend on the project
d. how much of the budget we really should have spent on the work completed so
far

e. None of these - ✔✔a

,Generally, the more metrics one adopts, the greater the project control. -
✔✔false


The Expected Time Complete (ETC) provides an estimate for completing the
scheduled work that remains. - ✔✔true


The cost incurred for completing a scheduled task or WBS component is the
a. Planned Value (PV)
b. Budget At Completion (BAC)
c. Actual Cost (AC)
d. Expected Time Complete (ETC)

e. Estimate at Completion (EAC) - ✔✔c


Earned Value-Actual Cost =
a. Cost performance index (CPI)
b. Scheduled performance index (SPI)
c. Cost Variance (CV)
d. Minimum funds needed (MFN)

e. None of these - ✔✔c


Information distribution includes all of the following EXCEPT:
a. Face-To-Face Meetings
b. Telephone, e-mail, and other wireless devices
c. Web-based technologies
d. None of these are examples of information distribution

, e. All of these are examples of information distribution - ✔✔e


Estimate at Completion (EAC) is __________
a. how much we actually spent for work completed
b. how much we budgeted to spend at the beginning of the project
c. how much of the budget we have left to spend on the project
d. how much of the budget we really should have spent on the work completed so
far

e. how much we spent to complete the project - ✔✔e


If a stakeholder has been judged too adversarial and having a vested interest in
the failure of your project, it would probably be wise to keep him/her out of the
communication loop. - ✔✔false


A project metric should be obtained from observable, quantifiable data that
allows the team and other stakeholders to gauge the efficiency and effectiveness
of the work being done. - ✔✔true


Budget At Completion (BAC) is __________
a. how much we actually spent for work completed
b. how much we budgeted to spend at the beginning of the project
c. how much of the budget we have left to spend on the project
d. how much of the budget we really should have spent on the work completed so
far

e. None of these - ✔✔b

Document information

Uploaded on
July 19, 2026
Number of pages
32
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
0
Followers
0
Items
1036
Last sold
-



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions