Examen

Florida Contractor's Manual Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Document preview thumbnail
Vista previa 4 fuera de 126 páginas

Florida Contractor's Manual Exam | Verified Exam Questions and Answers | Latest Updated Study Material 2026

Vista previa del contenido

Florida Contractor's Manual Exam | Verified Exam Questions and
Answers | Latest Updated Study Material 2026

Question:

A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner)
for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor
Answer:

A201: 3.3.2

Question:

Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers
Answer:

A201: 14.2.1

Question:

Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner

,3- Architect
4- Supplier
Answer:

A201: 1.5.1

Question:

Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be
required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due, unless 30 days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30
Answer:

A201: 15.2.1

Question:

Article 15) Claims and Disputes
15.2 Initial Decision
4- 30
The will on request furnish to a information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect
Answer:

A201: 9.6.3

,Question:

Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor
Answer:

A201: 5.3

Question:

Article 5) Subcontractors
5- 3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the Claim take
one or more of the following actions. Which of the following actions will NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request
Answer:

A201: 15.2.2

Question:

Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with a/an
to perform a portion of the Work at the site

, 1- Contractor
2- Subcontractor
3- Architect
4- Supplier
Answer:

A201: 5.1.2

Question:

Article 5) Subcontractors
5.1 Definitions
2- Subcontractor
If the Work is stopped for a period of consecutive
days through no fault of the Contractor, or Subcontractor, agents, employees or any other persons
performing portions of the Work under contract with the Contractor, the Contractor may
terminate the Contract and recover from the Owner
1- 120
2- 60
3- 30
4- 45
Answer:

A201: 14.1.4

Question:

Article 14) Termination or Suspension of the Contract
14.1 Termination by the Contractor
2- 60
What is the maximum amount of time after Substantial Completion of the Work shall all claims
(by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years

Información del documento

Subido en
16 de julio de 2026
Número de páginas
126
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$13.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
5
Seguidores
0
Artículos
4027
Última venta
1 semana hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes