Q: What is the lowest level of the work breakdown structure (WBS) called?
Answer:
Work package
Q: an output of a schedule model that presents linked activities with planned dates,
durations,
Answer:
milestones, and resources. Project schedule
Q: ______________________ dependencies are fixed and part of the natural flow
of work.
Answer:
Mandatory
,CAHIMS Certification - Complete Exam Study Guide with Questions
and Answers with Verified Solutions | Latest 2026 Update
Q: ________________ dependencies are flexible and call on the project manager to
exercise good
Answer:
judgment. Discretionary
Q: Which of the following is often used to graphically represent a project schedule?
Answer:
Gantt chart
Q: is a working document used for tracking project risks through completion of the
project.
Answer:
The
risk register
,CAHIMS Certification - Complete Exam Study Guide with Questions
and Answers with Verified Solutions | Latest 2026 Update
Q: The causes of a risk materializing into a negative event on a project are known
as risk
Answer:
triggers
Q: outlines what project information will be shared, who it will be shared with,
when the
Answer:
information will be shared, and how the information will be shared. The
communication
plan
Q: A _________________________ outlines who on the project team is assigned to
what project
Answer:
activities. responsibility assignment matrix
, CAHIMS Certification - Complete Exam Study Guide with Questions
and Answers with Verified Solutions | Latest 2026 Update
Q: Interactive communications
Answer:
Phone Calls
Q: Meetings
Answer:
Q: Pull communication
Answer:
Internet
Knowledge repositories
Q: Push communications
Answer:
Faxes and memos
Reports