Clean Water Act - ANSWER Law set into place in 1970 for storm water regulation
Immediately after project is awarded and before you begin any site work - ANSWER
When should you read and understand SWPP
Contaminated ground water - ANSWER What is not an allowable storm water discharge
or non-storm water discharge
When jurisdiction of operations specifies you can start - ANSWER When may construc-
tion activity begin
An officer and project owner - ANSWER SWPPPs certification are signed by who
303D list - ANSWER Waters that fail anti-degradation list are placed on which list.
FALSE - ANSWER The document that must be completed signed and submitted to the
state to obtain authorization to discharge is the NOT. (T/F)
All construction has been completed both inside and outside - ANSWER NOT can be filed
when
1
, is in charge of daily activities - ANSWER Operations on a construction site are the entity
in charge of plans and specification and the entity who?
Stay out of trouble with the law - ANSWER Motives for staying in compliance with storm
water objectives?
To protect and preserve beneficial use of U.S. waters, maintaining their clean, physical and
biological integrity - ANSWER Objectives of the clean water act are
National Pollutant Discharge Elimination System - ANSWER NPDES stands for
Site description and maps, inspection and maintenance procedure. Potential pollutant
sources, schedules of activities, site contact information, plan certification documents, site
contact info and descriptions of controls BMP - ANSWER Which are a component of a
good SWPPP
False - ANSWER Construction sediment is not considered a potential pollutant source
(T/F)
Project owner, SWPPP designer - ANSWER When modifying or substituting a storm wa-
ter BMP the contractor must consult with
False - ANSWER NOI must be submitted to the appropriate agency before the storm wa-
ter pollution preventive plan is developed (T/F)
False, 303d List - ANSWER Name of the list with impaired waters is called totally daily
maximum load (T/F)
Site specific - ANSWER A well constructed SWPPP for your site should be?