1. What is the primary role of a permit technician?
A. Conduct field inspections
B. Design structural plans
C. Process permit applications and assist applicants
D. Enforce criminal building penalties
Rationale: Permit technicians primarily handle application
intake, review completeness, and customer assistance, not
enforcement or design.
Correct Answer: C
2. Which document is typically required before issuing a
building permit?
A. Insurance policy
B. Approved construction plans
C. Utility bill
D. Property tax receipt
Rationale: Approved or review-compliant plans are required to
ensure code compliance before permits are issued.
Correct Answer: B
,3. What is zoning primarily concerned with?
A. Electrical safety
B. Land use and development control
C. Fire extinguisher placement
D. Plumbing design
Rationale: Zoning regulates land use, building placement, and
development standards.
Correct Answer: B
4. A permit technician should verify which of the following
first?
A. Contractor lunch schedule
B. Application completeness
C. Final inspection report
D. Building occupancy
Rationale: The first step is ensuring all required application
information is complete.
Correct Answer: B
5. What is a “building permit”?
A. A tax document
B. Legal authorization to begin construction work
C. A property deed
D. A utility approval
,Rationale: A building permit grants legal permission to begin
regulated construction activities.
Correct Answer: B
6. Which agency typically adopts building codes?
A. Local fire department
B. International Code Council (adopted by jurisdiction)
C. Real estate agencies
D. Insurance companies
Rationale: Jurisdictions adopt ICC model codes as regulatory
standards.
Correct Answer: B
7. What is the purpose of a site plan?
A. To show interior furniture layout
B. To show property boundaries and structure placement
C. To list materials used
D. To calculate taxes
Rationale: Site plans show property layout, setbacks, and
building location.
Correct Answer: B
8. What does “setback” refer to?
, A. Construction delay
B. Distance between structure and property line
C. Building height
D. Permit fee
Rationale: Setbacks regulate distance from property lines to
structures.
Correct Answer: B
9. Which department often reviews fire safety aspects of a
permit?
A. Water utility
B. Fire department
C. Postal service
D. Tax assessor
Rationale: Fire departments review fire safety compliance.
Correct Answer: B
10. What is a permit fee based on commonly?
A. Weather conditions
B. Project valuation
C. Contractor age
D. Number of inspectors available