VA DEQ ESC Inspector Exam Test Questions and Answers Graded A+

Document preview thumbnail
Vista previa 4 fuera de 35 páginas

VESCP Minimum Standard 1 Site NOT at Final Grade Site at Final Grade Minimum Standard 2 Minimum Standard 3 Virginia Erosion and Sediment Control Program - Administered by counties/cities (must), towns (may) - MUST BE APPROVED Stabilization permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; temporary soil stabiliza- tion shall be applied within seven days to denuded areas that may no

Vista previa del contenido

VA DEQ ESC Inspector Exam Test Questions and Answers Graded A+

Virginia Erosion and Sediment Control Program
VESCP
- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED
Stabilization

permanent or temporary soil stabilization shall be applied
to denuded areas within seven days after final grade is
reached on any portion of the site; temporary soil stabiliza-
Minimum Standard 1
tion shall be applied within seven days to denuded areas
that may not be at final grade but will remain dormant
for longer than 14 days; permanent stabilization shall be
applied to areas that are to be left dormant for more than
one year
- stabilize in 14 days
- temporarily seed
Site NOT at Final Grade
- mulch
- permanently stabilize if dormant > 1 year
- stabilize in 7 days (recommended immediately)
Site at Final Grade - permanently or temporarily seed and mulch
- mulch/matting/straw
Stock Piles, Waste and Borrow Areas

during construction, soil stock piles and borrow areas
shall be stabilized or protected with sediment trapping
Minimum Standard 2 measures

mulch prevents erosion by protecting the surface from
raindrop impact and silt fence intercepts and detains from
disturbed areas
Minimum Standard 3


,VA DEQ ESC Inspector Exam Test Questions and Answers Graded A+

Permanent Vegetation

permanent vegetation cover shall be established on de-
nuded areas not otherwise permanently stabilized (per-
manent vegetation shall not be considered established
until a ground cover is achieved that is uniform, mature
enough to survive, and will inhibit erosion *there is no %
associated with this*)

reduce erosion and decrease sediment yield from dis-
turbed area

this is the standard used to verify that a site is ready for
release of bonds or surety
First-Step Measures

Sediment basins and traps, perimeter dikes, sediment
barriers and other measures intended to trap sediment
shall be constructed as a first step in any land-disturbing
activity and shall be made functional before upslope land
disturbance takes place

a certain amount of initial land disturbance may be re-
Minimum Standard 4
quired to provide access for equipment to install the
perimeter controls, but site clearing and grading should
be kept to a minimum until the perimeter controls are in
place

intercepts and detains small amounts of sediment from
disturbed areas during construction operation to prevent
sediment from leaving the site and decrease velocity of
sheet flows and low-to-moderate level channel flow
Perimeter Controls


,VA DEQ ESC Inspector Exam Test Questions and Answers Graded A+

assures that sediment does not leave the perimeter of
the land-disturbing area once site clearing, grading, and
construction commences

Examples: silt fences, sediment traps, sediment basins,
construction entrance, temporary diversions, diversions
Earthen Structure Stabilization

stabilization measures shall be applied to earthen struc-
tures such as dams, dikes, and diversions immediately
Minimum Standard 5
after installation

reduce erosion and sedimentation and reduce damage
from sediment and runott to downstream or ott-site areas
Traps and Basins

Minimum Standard 6 sediment traps and basins shall be designed and con-
structed based upon the total drainage area (not just
disturbed area) to be served by the trap or basin
minimum storage capacity shall be 134 cubic yards per
acre of drainage area and shall only control drainage areas
Sediment Traps less than 3 acres

*stone outlet = trap*

surface runott from disturbed areas that is comprised
of flow from drainage areas greater than or equal to 3
acres shall be controlled by a basin; minimum storage
Sediment Basins capacity of a sediment basin shall be 134 cubic yards
per acre of drainage area; the outfall system shall, at a
minimum, maintain the structural integrity of the basin
during a 25-year storm of 24-hour duration; runott coef-


, VA DEQ ESC Inspector Exam Test Questions and Answers Graded A+

ficients used in runott calculations shall correspond to a
bare earth condition or those conditions expected to exist
while the sediment basin is utilized.
1. place near the lowest drainage points of a project

2. install as a first-step measure [MS-4]
Sediment Trapping Devises
3. stabilize immediately [MS-5]

4. must include outlet protection for basins [MS-11]
Cut and Fill Slopes

roughening the surface of the slope decreases runott,
lowers the velocity runott, increases water retention, and
leads to better seed germination
Minimum Standard 7
slopes that are found to be eroding excessively within
on year of permanent stabilization shall be provided with
additional slop stabilizing measures until the problem is
corrected

Concentrated Runott

shall not flow down cut or fill slopes unless contained with-
in an adequate temporary or permanent channel, flume
or slope drain structure
Minimum Standard 8
outlets of these drains need outlet protection to prevent
erosion from the concentrated flow

size of pipe depends on drainage area

temporarily conduct concentrated stormwater runott safe-

Información del documento

Subido en
3 de julio de 2026
Número de páginas
35
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$14.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
MERCYTRISHIA
3.9
(43)
Vendido
238
Seguidores
35
Artículos
14558
Última venta
2 semanas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes