● What is defined as "any of the project's specialist products (whether
tangible or intangible)". Answer: Output
● What is defined as "the measurable improvement resulting from an
outcome that is perceived as an advantage by a stakeholder". Answer:
Benefit
● What is the missing word(s) in the following sentence: "Dis-benefits
are ..................... of an activity". Answer: actual consequences
● Who is responsible for ensuring that those benefits specified by the
Senior User(s) represent value for money, are aligned to corporate
objectives, and are capable of being realized. Answer: Executive
● What are the missing word(s) from the following statement:
The ongoing and ever-present decision regarding the Business Case is
whether the project can (still) be justified. This is based on whether the
project is desirable (the cost/benefit/risk balance), viable (the project can
, .......................) and achievable (the products can provide the benefits).
Answer: deliver the products
● What are the missing word(s) from the following statement:
"The justification for the project is based on whether the project is
..............., viable and achievable". Answer: desirable
● Which theme has as its' purpose "establishes mechanisms to judge
whether the project is (and remains) desirable, viable and achievable.
Answer: Business Cas
● Identify the PRINCE2 Management product Purpose from which the
quotation below is taken:
"used to define how and when a measurement of the achievement of the
project's benefits expected by the Senior User can be made". Answer:
Benefits Review Plan
● Identify the PRINCE2 Management product Purpose from which the
quotation below is taken:
"used to document the justification for the undertaking of a project,
based on the estimated costs (of development, implementation and
incremental ongoing operations and maintenance costs) against the
UPDATED SCRIPT 2026 PRACTICE
SOLUTIONS GRADED A+
● What is defined as "any of the project's specialist products (whether
tangible or intangible)". Answer: Output
● What is defined as "the measurable improvement resulting from an
outcome that is perceived as an advantage by a stakeholder". Answer:
Benefit
● What is the missing word(s) in the following sentence: "Dis-benefits
are ..................... of an activity". Answer: actual consequences
● Who is responsible for ensuring that those benefits specified by the
Senior User(s) represent value for money, are aligned to corporate
objectives, and are capable of being realized. Answer: Executive
● What are the missing word(s) from the following statement:
The ongoing and ever-present decision regarding the Business Case is
whether the project can (still) be justified. This is based on whether the
project is desirable (the cost/benefit/risk balance), viable (the project can
, .......................) and achievable (the products can provide the benefits).
Answer: deliver the products
● What are the missing word(s) from the following statement:
"The justification for the project is based on whether the project is
..............., viable and achievable". Answer: desirable
● Which theme has as its' purpose "establishes mechanisms to judge
whether the project is (and remains) desirable, viable and achievable.
Answer: Business Cas
● Identify the PRINCE2 Management product Purpose from which the
quotation below is taken:
"used to define how and when a measurement of the achievement of the
project's benefits expected by the Senior User can be made". Answer:
Benefits Review Plan
● Identify the PRINCE2 Management product Purpose from which the
quotation below is taken:
"used to document the justification for the undertaking of a project,
based on the estimated costs (of development, implementation and
incremental ongoing operations and maintenance costs) against the