Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Examen

CERTIFIED CONSTRUCTION MANAGER (CCM) PRACTICE EXAM 1 QUESTIONS AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS RATIONALES 2026 Q&A | INSTANT DOWNLOAD PDF.

Puntuación
-
Vendido
-
Páginas
34
Grado
A+
Subido en
01-07-2026
Escrito en
2025/2026

CERTIFIED CONSTRUCTION MANAGER (CCM) PRACTICE EXAM 1 QUESTIONS AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS RATIONALES 2026 Q&A | INSTANT DOWNLOAD PDF.

Institución
3x@m
Grado
3x@m

Vista previa del contenido

CERTIFIED CONSTRUCTION MANAGER (CCM) PRACTICE EXAM 1 QUESTIONS AND CORRECT
ANSWERS (VERIFIED ANSWERS) PLUS RATIONALES 2026 Q&A | INSTANT DOWNLOAD PDF.



CORE DOMAINS
* Project Management Fundamentals
* Cost Management
* Time Management
* Quality Management
* Contract Administration
* Safety and Risk Management
* Professional Practice and Ethics
* Sustainability and Environmental Compliance


INTRODUCTION
*The purpose of this practice exam is to evaluate a candidate’s readiness for the Certified Const
 




SECTION ONE: QUESTIONS 1–100
Which document serves as the primary instrument for establishing the scope, schedule, and budget
constraints at the onset of a project?
A. Project Charter
B. Work Breakdown Structure
C. Basis of Design
D. Statement of Work

,🟢A
🔴 RATIONALE: The Project Charter formally authorizes the existence of a project and provides the
project manager with the authority to apply organizational resources to project activities.
A contractor identifies a differing site condition that was not visible during the bidding process. What
is the immediate professional step?
A. Stop all work until the owner pays for an investigation.
B. Proceed with the work to avoid schedule delays.
C. Provide written notice to the owner before disturbing the condition.
D. Immediately file a formal claim for extra costs.
🟢C
🔴 RATIONALE: Contractual requirements typically mandate that the contractor notify the owner in
writing immediately upon discovery of a differing site condition, allowing the owner to investigate
before work continues.
Which project delivery method typically allows for the most significant overlap between the design
and construction phases?
A. Design-Bid-Build
B. Design-Build
C. Construction Management at Risk
D. Integrated Project Delivery
🟢B
🔴 RATIONALE: Design-Build integrates the design and construction functions under a single
contract, enabling fast-tracking through concurrent design and construction activities.
In a Critical Path Method (CPM) schedule, what does "total float" represent?
A. The time a task can be delayed without affecting the project completion date.
B. The difference between early start and late start.

,C. The duration of the longest path in the network.
D. The amount of time a task can be delayed without affecting its successor.
🟢A
🔴 RATIONALE: Total float is the amount of time a schedule activity can be delayed or extended
from its early start date without delaying the project finish date.
Which type of contract involves the owner reimbursing the contractor for actual costs and paying a
fixed fee for overhead and profit?
A. Lump Sum
B. Unit Price
C. Cost Plus Fixed Fee
D. Guaranteed Maximum Price
🟢C
🔴 RATIONALE: Cost Plus Fixed Fee contracts provide for payment of actual costs plus a pre-
negotiated fixed fee, which does not change based on actual cost fluctuations.
What is the primary purpose of a Quality Assurance (QA) program?
A. To detect defects in the final product.
B. To ensure processes are in place to prevent defects during construction.
C. To verify that all materials meet ASTM standards.
D. To monitor the performance of subcontractors.
🟢B
🔴 RATIONALE: Quality Assurance focuses on the processes and procedures used to manage the
work to prevent defects from occurring, as opposed to Quality Control which identifies them.
An ethics violation occurs when a construction manager accepts a gift from a potential supplier.
Which principle is primarily compromised?
A. Competence

, B. Confidentiality
C. Integrity
D. Fairness
🟢C
🔴 RATIONALE: Accepting gifts creates a conflict of interest, directly undermining the integrity and
impartial judgment required of a construction manager.
When calculating the Cost Performance Index (CPI), a value of 0.85 indicates:
A. The project is under budget.
B. The project is 15% behind schedule.
C. The project is over budget.
D. The project is performing at 85% of its estimated value.
🟢C
🔴 RATIONALE: A CPI of less than 1.0 indicates that the cost of work performed is greater than the
budgeted cost, signifying that the project is over budget.
Which insurance policy is intended to cover the loss of or damage to the building under
construction?
A. Commercial General Liability
B. Builder’s Risk
C. Workers’ Compensation
D. Professional Liability
🟢B
🔴 RATIONALE: Builder’s Risk insurance is property insurance that indemnifies against loss or
damage to the building while it is under construction.
What is the primary goal of the "Punch List" phase?
A. To determine the final project cost.

Escuela, estudio y materia

Institución
3x@m
Grado
3x@m

Información del documento

Subido en
1 de julio de 2026
Número de páginas
34
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$25.99
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor
Seller avatar
tutorcase
1.0
(1)

Conoce al vendedor

Seller avatar
tutorcase For state PCS, UPSC, UGC NET
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2
Miembro desde
1 mes
Número de seguidores
0
Documentos
818
Última venta
1 semana hace

1.0

1 reseñas

5
0
4
0
3
0
2
0
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes