Concrete slab shrinkage cracks are primarily reduced by:
| | | | | | |
Select one:
|
a. selecting a good concrete mix
| | | | |
b. adding wire-mesh rebar
| | | |
c. providing proper slab finishing
| | | |
d. adding a vapor retarder under the slab
| | | | | | |
e. adding a drainage layer below the slab. - CORRECT ANSWER✔✔-b.
| | | | | | | | | | |
adding wire-mesh rebar
| |
Form ties are associated with which concrete element?
| | | | | | |
Select one:
|
a. Spread footings
| |
b. Elevated slab
| |
,c. Walls
| |
d. Slab on grade
| | |
e. Caissons - CORRECT ANSWER✔✔-c. Walls
| | | | |
In slab placement, what comes directly before concrete floating?
| | | | | | | |
Select one:
|
a. Form work placement
| | |
b. Curing
|
c. Troweling
|
d. Pouring
|
e. Strike-off - CORRECT ANSWER✔✔-e. Strike-off
| | | | |
Insulating concrete forms (ICFs):
| | |
Select one:
|
a. place the insulation at the core of the concrete wall.
| | | | | | | | | | |
b. can be filled with concrete in a high-lift operation.
| | | | | | | | | |
, c. come in entire-wall size.
| | | | |
d. are interlocking blocks that can be placed easily.
| | | | | | | | |
e. are forms made of insulating concrete. - CORRECT ANSWER✔✔-a.
| | | | | | | | | |
place the insulation at the core of the concrete wall.
| | | | | | | | |
Reshoring is: |
Select one: |
a. form work for a column.
| | | | | |
b. a second set of form work for a wall.
| | | | | | | | | |
c. a set of supports for lower floors while upper floors get poured.
| | | | | | | | | | | | |
d. a preparation for post-tensioning of slabs.
| | | | | | |
e. form work that holds a concrete slab while it is being poured. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-c. a set of supports for lower floors while upper
| | | | | | | | | | |
floors get poured.
| |
Slip forming would be most beneficial when constructing:
| | | | | | |
Select one: |
a. elevator shafts or storage silos.
| | | | | |
With Correct Answers
Concrete slab shrinkage cracks are primarily reduced by:
| | | | | | |
Select one:
|
a. selecting a good concrete mix
| | | | |
b. adding wire-mesh rebar
| | | |
c. providing proper slab finishing
| | | |
d. adding a vapor retarder under the slab
| | | | | | |
e. adding a drainage layer below the slab. - CORRECT ANSWER✔✔-b.
| | | | | | | | | | |
adding wire-mesh rebar
| |
Form ties are associated with which concrete element?
| | | | | | |
Select one:
|
a. Spread footings
| |
b. Elevated slab
| |
,c. Walls
| |
d. Slab on grade
| | |
e. Caissons - CORRECT ANSWER✔✔-c. Walls
| | | | |
In slab placement, what comes directly before concrete floating?
| | | | | | | |
Select one:
|
a. Form work placement
| | |
b. Curing
|
c. Troweling
|
d. Pouring
|
e. Strike-off - CORRECT ANSWER✔✔-e. Strike-off
| | | | |
Insulating concrete forms (ICFs):
| | |
Select one:
|
a. place the insulation at the core of the concrete wall.
| | | | | | | | | | |
b. can be filled with concrete in a high-lift operation.
| | | | | | | | | |
, c. come in entire-wall size.
| | | | |
d. are interlocking blocks that can be placed easily.
| | | | | | | | |
e. are forms made of insulating concrete. - CORRECT ANSWER✔✔-a.
| | | | | | | | | |
place the insulation at the core of the concrete wall.
| | | | | | | | |
Reshoring is: |
Select one: |
a. form work for a column.
| | | | | |
b. a second set of form work for a wall.
| | | | | | | | | |
c. a set of supports for lower floors while upper floors get poured.
| | | | | | | | | | | | |
d. a preparation for post-tensioning of slabs.
| | | | | | |
e. form work that holds a concrete slab while it is being poured. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-c. a set of supports for lower floors while upper
| | | | | | | | | | |
floors get poured.
| |
Slip forming would be most beneficial when constructing:
| | | | | | |
Select one: |
a. elevator shafts or storage silos.
| | | | | |