Florida Construction Lien Law: Sections 713.011-713.13
Study guide
paul_93307
Terms in this set (178) Hide definitions
What happens if the last day of a The time period is extended to the end of the next
time period falls on a Saturday, business day.
Sunday, or holiday?
What occurs if the clerk's office is The time period for recording a document or filing
closed due to an emergency? an action is tolled and extended by the number of
days the office was closed.
, What is required for written notices, They must be in writing, except for those required
demands, or requests under Florida's by s. 713.14.
construction lien law?
What is the minimum contract Any direct contract greater than $2,500.
amount that requires a specific
notice provision in Florida?
What must the notice provision in a It must inform that unpaid workers or suppliers may
direct contract state? enforce a claim for payment against the property.
What is a construction lien? A claim against a property for unpaid labor or
materials provided.
What happens if a contractor fails to Subcontractors may file a lien against the property
pay subcontractors? for payment.
What must a contractor provide A written release of lien from any person or
before any payment is made to company that has provided a 'Notice to Owner.'
protect the owner?
What is the consequence of failing to It does not bar the enforcement of a lien against a
provide the required written notice? person who has not been adversely affected.
713.011-713.13
Leave the first rating
Save
Students also studied
From the same upload Flashcard sets Study guides
Florida Construction Lien Law: Sections 713.011-713.13
Study guide
paul_93307
Terms in this set (178) Hide definitions
What happens if the last day of a The time period is extended to the end of the next
time period falls on a Saturday, business day.
Sunday, or holiday?
What occurs if the clerk's office is The time period for recording a document or filing
closed due to an emergency? an action is tolled and extended by the number of
days the office was closed.
, What is required for written notices, They must be in writing, except for those required
demands, or requests under Florida's by s. 713.14.
construction lien law?
What is the minimum contract Any direct contract greater than $2,500.
amount that requires a specific
notice provision in Florida?
What must the notice provision in a It must inform that unpaid workers or suppliers may
direct contract state? enforce a claim for payment against the property.
What is a construction lien? A claim against a property for unpaid labor or
materials provided.
What happens if a contractor fails to Subcontractors may file a lien against the property
pay subcontractors? for payment.
What must a contractor provide A written release of lien from any person or
before any payment is made to company that has provided a 'Notice to Owner.'
protect the owner?
What is the consequence of failing to It does not bar the enforcement of a lien against a
provide the required written notice? person who has not been adversely affected.