Administered by the US environmental protection agency (EPA) Created the NPDES - Answer 1972 clean water act Amendment to CWA CALLED WATER QUALITY ACT - Answer 1987 South Carolina is NPDES delegated state. - Answer NPDES in south carolina SCDHEC - Answer NPDES regulations are administered by stormwater discharges from construction sites - Answer CGP authorizes land disturbing activities greater than or equal to 1 acre -land disturbance less than 1 ac within 1/2 miles of water body in SC costal zone - Answer Who must obtain NPDES coverage operator-person or company for a particular discharge - Answer NPDES permits are issued to -has day to day operational control to ensure compliance with SWPP -typically the owner or developer - Answer primary permittee submit NOI, Preparation of the C_SWPPP - Answer primary permittee responsibilities individual lot owner or residential builder that conducts land disturbing activity limited to an individual lot or group of lots as part of approved LCP of development - Answer Secondary permittee must on Contractor Certification- D-0437 - Answer contractors SCDHEC CGP, NOI, NPDES coverage approval letter, Contractor Certifications, Local Approvals, USACE approvals, Critical area permit(coast) - Answer On-Site SWPPP

Vista previa del contenido

SC: CEPSCI- PRACTICE TEST
Questions All Solved Correct Graded
A+
Administered by the US environmental protection agency (EPA) Created the NPDES - Answer
1972 clean water act



Amendment to CWA CALLED WATER QUALITY ACT - Answer 1987



South Carolina is NPDES delegated state. - Answer NPDES in south carolina



SCDHEC - Answer NPDES regulations are administered by



stormwater discharges from construction sites - Answer CGP authorizes



land disturbing activities greater than or equal to 1 acre

-land disturbance less than 1 ac within 1/2 miles of water body in SC costal zone - Answer
Who must obtain NPDES coverage



operator-person or company for a particular discharge - Answer NPDES permits are issued to



-has day to day operational control to ensure compliance with SWPP

-typically the owner or developer - Answer primary permittee



submit NOI, Preparation of the C_SWPPP - Answer primary permittee responsibilites



individual lot owner or residential builder that conducts land disturbing activity limited to an
individual lot or group of lots as part of approved LCP of development - Answer Secondary
permittee



must on Contractor Certification- D-0437 - Answer contractors



SCDHEC CGP, NOI, NPDES coverage approval letter, Contractor Certifications, Local Approvals,
USACE approvals, Critical area permit(coast) - Answer On-Site SWPPP

, a copy of signed and certified SWPPP, NOI, and CGP coverage letter from DHEC must be retained
at site or electronically accessible - Answer OS_SWPPP



minor modifications made directly in the field,do not need approval by DHEC- additional BMP's,
removal of disturbed areas - Answer minor modification to ON-SWPPP



must be made by qualified individual and submitted to DHEC or appropriate delegated entity for
approval - Answer major modifications to OS-SWPPP



include a phased stormwater management plan which identifies all BMP's and grading work
conducted during a specific portion of the sites construction sequence. Each phase identified on
at least one separate plan sheet. - Answer Phased plan requirement > 5



at least two separate plan phases are required - initial land disturbance phase - stabilization
phase - Answer Phased plan requirement < 10 but > 5 acres



at least 3 separate plan phases are required - initial land disturbance phase - construction phase
- stabilization phase - Answer Phased plan requirement ≥ 10 acres



1. areas of site disturbed by construction activity and areas used for storage of materials
exposed to precipitation

2. stormwater conveyance systems for evidence of sediment

3. BMP's identified in OS-SWPPP

4. Discharge location to investigate if sediment leaving site, or if such locations are inaccessible,
nearby downstream location if possible.

5. Where vehicles enter or exit site for evidence of off-site sediment tracking. - Answer All
compliance inspection must include invesg. of, at a minimum of 5 of the following



at least once a week or within 24 hours of end of storm event >0.5 inches - Answer
inspection frequency after construction begins



Once every month - Answer Inspection frequency for sites that have reached temporary
stablization



linear activites may limit access to disturbed areas, in such cases representative inspections may
be performed - Answer Linear site inspection



personnel must investigate BMP's along the site for 0.25 miles above and below each access
point where the site intersects with -roadway - undisturbed right of way - other similar feature-

Información del documento

Subido en
15 de junio de 2026
Número de páginas
12
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$13.89

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TestSolver9
3.5
(165)
Vendido
955
Seguidores
127
Artículos
30581
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes