OPMA 3306 CH 5 EXAM QUESTIONS
AND ANSWERS



The variance of an activity's completion time requires knowledge of The __________
time and the _________ time - Correct Answers -optimistic, pessimistic

Slack activity time is the difference between the early start and the late finish of a
project activity time. - Correct Answers -F

The critical path in a project is that sequence of activities that consume the longest
amount of time in a project network of activities. - Correct Answers -T

A matrix project attempts to blend properties of functional and pure project structures. -
Correct Answers -T

Earned Value Management (EVM) has the capability to combine measurements of
scope, schedule, and cost in a project. - Correct Answers -T

In a Gantt chart the horizontal axis is usually which of the following? - Correct Answers -
Time

You have been placed in charge of a large project. Shortened communication lines are
required to ensure quick resolution of problems as they arise. You recognize that the
project is going to take a lot of time and require a lot of team pride, motivation, and
commitment by all members. Which project management structure should you use in
this situation? - Correct Answers -Pure project

In CPM analysis it is generally expected that the relationship between activity direct
costs and project indirect costs will be which of the following? - Correct Answers -
Negatively related

The costs associated with sustaining a project are referred to as... - Correct Answers -
indirect costs

A _________ __ ______ is a written description of the objectives to be achieved during
a project - Correct Answers -statement of work

A work package includes _____________ measures - Correct Answers -performance

, A work package includes _________________ and ________________ times for a
group of activities - Correct Answers -starting, completion

A work package includes a _________________ of what is to be done - Correct
Answers -description

Rank these terms from highest level down to lowest - Correct Answers -Portfolio,
Project, Task, Subtask, Work package

It is not possible to have a process change project that accommodates a large amount
of change - Correct Answers -F

In a network diagram, the activities that lead directly to another activity are known as
___________ predecessors - Correct Answers -immediate

Gantt charts show the amount of __________ and the sequence of ____________ -
Correct Answers -time, activities

There are relatively few project management software options for practitioners - Correct
Answers -F

In the ___________ process, the during of an activity is reduced - Correct Answers -
crashing

What are general types of projects? - Correct Answers -derivative, breakthrough,
platform

What is the first step in the critical path method? - Correct Answers -Identify each
activity and its duration

What is the second step in the critical path method? - Correct Answers -Construct a
network showing the precedence relationships among activities

What is the third step in the critical path method? - Correct Answers -Determine the
critical path

What is the last step in the critical path method? - Correct Answers -Determine the early
start/early finish and late start/late finish schedule

The hierarchy of project tasks, subtasks and work packages is known as a work
breakdown structure - Correct Answers -T

An advantage of a functional project is that team members can work on multiple
projects at once - Correct Answers -T

Información del documento

Subido en
10 de mayo de 2026
Número de páginas
6
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
millyphilip
3.6
(555)
Vendido
2955
Seguidores
1963
Artículos
45759
Última venta
18 horas hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes