ACTUAL EXAM PAPER 2026 QUESTIONS
WITH ANSWERS GRADED A+
◍ Monitor Risks, Inputs.
Answer: Project management plan, project documents, work performance
data, work performance reports
◍ Monitor and Control Project Work, Outputs.
Answer: Work performance reports, change requests, PM plan updates, and
proj. docs updates
◍ Sequence Activities, Inputs.
Answer: Project Management Plan, Project documents, EEFs, OPAs
◍ Control Quality, Outputs.
Answer: Quality control measurements, Verified deliverables, Work
performance information, Change requests, Project Management Plan
updates, Project document updates
◍ Perform Integrated Change Control, Tools & Techniques.
Answer: Expert judgement, change control tools, data analysis, decision
making, and meetings
◍ Manage Communications, Inputs.
Answer: Project Manage Plan, Project documents, Work performance
reports, EEFs, OPAs
◍ Define Scope, Outputs.
Answer: Project scope statementProject documents updates
◍ Validate Scope, Tools and Techniques.
Answer: Inspection, Decision making
,◍ Conduct Procurements, Outputs.
Answer: Selected sellers, Agreements, Change requests, Project
Management Plan updates, Project document updates, OPA updates
◍ Question part of PQ3R.
Answer: Turn objectives into questions, and form questions about material
◍ Critical thinking, ensure that you approach a topic with what?.
Answer: An open mind and the focus on reliable evidence
◍ Monitor and Control Project Work, Inputs.
Answer: PM plan, proj. docs, work performance information, agreements,
enter. enviro. factors, and org. process assets
◍ Conduct Procurement, Inputs.
Answer: Project management plan, project documents, procurement
documentation, seller proposals, EEFs, OPAs
◍ Conduct Procurements, Tools & Techniques.
Answer: Expert judgement, advertising, bidder conferences, data analysis,
interpersonal and team skills
◍ time management skills.
Answer: Be mindful of motivesPractice consistent, restorative sleep habits
Monitor gathering points to keep track of activities Listen as though you
will be teaching Process all you have done and learned at the end of each
day
◍ Develop Schedule, Inputs (sc).
Answer: Project Management Plan, Project documents, Agreements, EEFs,
OPAs (sc)
◍ Plan Risk Management, Tools & Techniques.
Answer: Expert judgement, Data analysis, Meetings
◍ Control Costs, Inputs.
Answer: project management plan, project funding requirements, work
performance data, organizational process assets
, ◍ Perform Qualitative Risk Analysis, Tools & Techniques.
Answer: Expert judgement, data gathering, data analysis, interpersonal and
team skills, risk categorization, data representation, and meetings
◍ Plan Scope Management, Tools & Techniques (s).
Answer: Expert judgement, Data analysis, Meetings (s)
◍ Perform Quantitative Risk Analysis, Tools & Techniques.
Answer: Expert judgement, data gathering, interpersonal and team skills,
representations of uncertainty, data analysis
◍ Plan Cost Management, Inputs.
Answer: Project Charter, Project Management Plan, EEFs, OPAs
◍ Manage Communications, Outputs.
Answer: Project communications, Project Management Plan updates, Project
document updates, OPA updates
◍ Estimate Activity Durations, Outputs.
Answer: Duration estimates, Basis of estimates, Project document updates
◍ Control Scope, Tools & Techniques.
Answer: Data analysis
◍ What does smart stand for?.
Answer: Specific, Measurable, Attainable, Realistic, Timely
◍ Identify Stakeholders, Outputs.
Answer: Stakeholder register, Change requests, Project Management Plan
updates, Project document updates
◍ Plan Schedule Management, Inputs.
Answer: Project Charter, Project Management Plan, EEFs, OPAs
◍ Define Scope, Tools & Techniques.
Answer: Expert judgement, Data analysis, Decision making, Interpersonal
and team skills, Product analysis
◍ Plan Scope Management, Outputs.