COSC 275 FINAL EXAM REVIEW QUESTIONS

Quantification - Answers - In estimating an activity to translate project scope information
into resource quantities suitable for costing. In the engineering and construction
industry, a takeoff is a specific type of quantification that is a measurement and listing of
quantities of materials from drawings

Quantities - Answers - Measured amounts of construction items expressed in their
customary units.

Estimating - - Answers - The anticipated cost of materials, labor, equipment, or any
combination of these for a proposed construction project.

Activity - - Answers - In critical path method (CPM) scheduling, a task or item of work
required to complete a project. Also called task.

Project - - Answers - the job as a whole

Scope - - Answers - An accurate, detailed, and concise description of the work to be
performed by the contractor, the owner, and third parties in a construction contract.

Measurement - - Answers - A quantity survey from plans or a field survey of work to be
done.

Material - - Answers - Any product or substance specified for use in the construction of
a project.

Drawings - - Answers - The portion of the contract documents that gives a graphic
representation of the work to be done in the construction of a project.

Specifications - - Answers - a detailed and exact statement of particulars, especially a
statement prescribing materials, dimensions, and workmanship for something to be built
or installed

Dimensions - - Answers - the distance between two points, lines, or planes

Workmanship - - Answers - the quality of work performed

Specs - - Answers - contraction of specifications

Specification or specs - - Answers - Documents that define the qualitative requirements
for products, materials, and workmanship upon which the contract for construction is
based.

, Contract for construction - - Answers - An agreement between owner and contractor
whereby the contractor agrees to construct the owner's project in accordance with the
contract documents, within a specified amount of time, and for consideration to be paid
by the owner as mutually agreed.

Area - - Answers - A measurement of a given planar region or of the surface of a solid.
A particular part of a building that has been set aside for a specific purpose.

Area method - - Answers - A construction cost estimating system employing unitsquare
foot costs multiplied by the adjusted gross floor area of a building.

Linear measurement - - Answers - A unit or system of units for measuring length: 12" =
1', 3' = 1 yard, 1 yard = 0.9144 meters, 1 mile = 5,280 feet.

Length - - Answers - the longest dimension of an object

Yard - - Answers - A unit of length in the English system equal to 3'. A measure of
concrete. One cubic yard = 3' x 3' x 3' in volume, or 27 cubic feet. A term applied to that
part of a plot not occupied by the building or driveway.

Where do i start? Scope? - Answers - First thing you need to know before you make a
quantitative estimate you need to know the scope (plans, specs, and simply put the list
of things you have to do in order of sequence of when they need to be done in relation
to each other)
Second step is to begin take offs but preparations are necessary such as contract
documents
You quantify it in the same way and order that you build it

Divisions of construction - Answers - Division 0 - general condition
Division 1 - General requirements
Division 2 - Existing condition
Division 3 - concrete
Division 4 - masonry
Divisio n 5 - metal
Division 6 - wood and plastics
Division 7 - thermal and moisture protection
Division 8 - doors and windows
Division 9 - finishes
Division 10 - specialties
Division 11 - Equipment
Division 12 - furnishings
Division 13 - Special construction
Division 31 - earthworks
Division 32 - exterior improvements

Información del documento

Subido en
25 de marzo de 2026
Número de páginas
8
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$14.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GEEKA
3.8
(366)
Vendido
2163
Seguidores
1449
Artículos
60418
Última venta
1 día hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes