CEP Exam with all Correct & 100% Verified Answers |Latest Version |Already Graded A+

Document preview thumbnail
Vista previa 2 fuera de 11 páginas

CEP Exam with all Correct & 100% Verified Answers |Latest Version |Already Graded A+

Vista previa del contenido

CEP Exam with all Correct & 100% Verified Answers |
Latest Version |Already Graded A+

Estimating ✔Correct Answer-A prediction or forecast of resources (Time, Cost and Materials)
required to achieve or obtain an agreed upon scope.

role of a cost estimator ✔Correct Answer-Predict cost of a project for a defined scope, to be
completed at defined location and point if time in future. - Assists in economic evaluation of
potential projects. - Collect and analyze data

budgeting ✔Correct Answer-A process used to allocate the estimated costs of resources into cost
accounts against which cost performance will be measured and assessed. Budgeting considers time-
phase in relation to a schedule and/or time based financial requirements and constraints.

quantification? ✔Correct Answer-Activity to translate project scope information into resource
quantities suitable for costing

Class 5 ✔Correct Answer-conceptual/screening - factored/parametric

Class 4 ✔Correct Answer-Study/Feasibility - equipment factored/parametric

Class 3 ✔Correct Answer-Budget/Authorizing/Control - semi detailed line items.

Class 2 ✔Correct Answer-Control/Bid Tender - detailed unit costs/ forced take off

Class 1 ✔Correct Answer-Check estimate - detailed take off

Costing ✔Correct Answer-Costing is the application of cost and resources to a quantified scope.

Pricing ✔Correct Answer-The determination of the amount of money asked in exchange for the
item, it is applies after costing and its determination takes in consideration; business and other
considerations in addition to inherent costs

fundamental considerations for internalization ✔Correct Answer-Converting units from other
measurement systems, calculate the effects of changes in currency exchange rates and adjust labor
productivity.

accuracy ✔Correct Answer-It is an indication of the degree to which the final cost outcome for a
given project will vary from the original estimate cost

Contingency ✔Correct Answer-It is an amount added to an estimate to allow for items, conditions
or events for which the state occurrence or effect is uncertain and that experience shows will likely
result in additional costs.

Parametric estimate ✔Correct Answer-Is the process of estimating cost by using mathematical
equations that relate cost to one or more physical variables associated with the item being
estimated.

, Cost Estimate Relationship (CER) ✔Correct Answer-It is an algorithm or formula that is used to
perform the costing operation. CER's relate (Cost, Time, and Quantity) with quantity scope, execution
strategies or other defining elements.

Location Factor ✔Correct Answer-An overall total project factor for translating the summation of
all project cost elements from a
geographical location to another.

Life Cycle Costs ✔Correct Answer-Consideration of all costs of a product, from concept, design,
implementation, start up and
dismantling.

Direct Costs ✔Correct Answer-The costs related to completing work that are directly attributable
to its performance and are necessary for its completion. It includes the supervision directly involved
in the physical

Indirect Costs ✔Correct Answer-The cost not directly attributable to the completion of an activity,
typically allocated across all activities on a predetermined basis.

Lang Factor ✔Correct Answer-It is a technique proposed by H. J. Lang. Lang suggested multiplying
the cost of the equipment by a factor (Lang Factor) to obtain total process plant cost. Total plant Cost
= Total equipment cost x Lang factor

Hand Factor ✔Correct Answer-Hand factor method uses different factor for different types of
equipment. Different from Lang factor method when the cost of the equipment are multiplied by its
factors we obtain the direct field costs. Indirect field costs, home office costs and OSBL costs are
excluded from the final result. Direct field Cost = Equipment cost x Hand factor

Average crew Composite rate ✔Correct Answer-They are the same and consist in develop an
average rate between crafts of different experiences and wage rates.

Bureden ✔Correct Answer-It is the cost of maintaining an office with staff, other than operating
personnel. Also includes federal, state and local taxes, fringe benefits and other union contract
obligations

Bare Rate ✔Correct Answer-Bare labor rate is the gross direct wage paid to the worker

unbalance estimate technique ✔Correct Answer-It is a technique used to allocate estimate costs to
accounts whose definitions do not reflect the nature of the cost being allocated. The objective is to
achieve a desired business result, such improve cash flow.

estimate process steps ✔Correct Answer-Scoping Quantification Costing Pricing Conditioning

KSA ✔Correct Answer-Knowledge, skills and abilities

Cost Category ✔Correct Answer-A division in a system of classification for estimated and expensed
money for which cost are to be
summarized.

Información del documento

Subido en
24 de marzo de 2026
Número de páginas
11
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$20.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Studyclub
3.6
(14)
Vendido
65
Seguidores
1
Artículos
12651
Última venta
1 día hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes