CAPM PRACTICE EXAM QUESTIONS AND ANSWERS


You notice that a project using the predictive approach is behind schedule for four out of
the five weeks. You perform a trend analysis and predict that the project will also be
behind this week. You are in the process of submitting a change request to get the
schedule back on track. What process group are you in?
a. Initiating
b. Planning
c. Monitoring and Controlling
d. Closing - Answers -c. Monitoring and Controlling

Explanation:


Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
01 - Becoming a Certified Associate in Project Management (CAPM)

Jason was recently hired to create a new product. The product will be complex and will
require many years to complete and involve many stakeholders from various groups.
Jason has decided it will be best to break up the product into smaller subprojects that
are managed separately. What is Jason managing?

a. Program
b. Portfolio
c. Project
d. Operations - Answers -a. Program

Explanation:
A program consists of similarly grouped projects.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

Which of the following are not project constraints?

a. Scope, quality, and schedule
b. Scope, cost, and schedule
c. Resource, risk, and cost
d. Procurement, issues, and opportunities - Answers -d. Procurement, issues, and
opportunities

,Explanation:
Scope, quality, schedule, budget/cost, resources, and risks are some of the most
important project constraints.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

In a project, laws, compliance, and regulatory requirements are considered:

a. assumptions
b. constraints
c. negotiable
d. irrelevant - Answers -b. constraints

Explanation:
Failing to comply with government agencies and regulations can have an impact on a
project, and the government should therefore be considered stakeholders. Any
specifications and requirements by the government would therefore be considered
constraints.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

You will be the project manager for a new project involving a globally distributed team
across many countries. To mitigate conflict with functional managers, you ask the
project sponsor for assistance. What should be done?

a. Create a project charter and list the authority and responsibilities of the project
manager.
b. Meet with every functional manager and inform them you have control of their teams.
c. Create a human resources plan.
d. Meet with every team member and inform them that you are in charge. - Answers -a.
Create a project charter and list the authority and responsibilities of the project
manager.

Explanation:
Because the project manager will have to compete with functional managers for team
members' time, the project charter would be the best place to outline how much
authority manager has over the project.

Domain:

,I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

Which of the following is not an attribute of a project?

a. Definitive start date
b. Definitive end date
c. Ongoing with no definitive end date
d. Results in a product, service, or result - Answers -c. Ongoing with no definitive end
date

Explanation:
Projects, by definition, are temporary. A project has definitive start and end dates and
results in a product, service, or result.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

You have been assigned to a project to open a new veterinary clinic. You need to meet
with the identified stakeholders to determine the best ways to communicate with them
and to get them engaged. What process group are you in?

a. Initiating
b. Planning
c. Executing
d. Monitoring and Controlling - Answers -b. Planning

Explanation:
You are in the Planning process group because you are meeting with the identified
stakeholders to identify how they should be communicated with and to keep them
engaged. This is done during planning.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

A stakeholder is saying they are not receiving project status reports frequently enough.
You review the communication management plan and discover some discrepancies.
You submit a change request to address the stakeholder's communication change.
What process group are you in?

a. Initiating

, b. Planning
c. Executing
d. Monitoring and Controlling - Answers -d. Monitoring and Controlling

Explanation:
You are in the Monitoring and Controlling process group because the communication
preference and frequency that were agreed upon in the plan are not being met. By
submitting a change request, you are monitoring the situation and taking control by
addressing the discrepancy. You are performing the integrated change control process.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

Jacob is joining a new project. His manager informs him that the requirements of the
project will be defined using progressive elaboration. Which of these options best
describes this?

a. The requirements will be defined iteratively over time.
b. The requirements will be defined up front.
c. The requirements are unknown and will be defined later.
d. The requirements will be defined based on discussions with the stakeholders at the
beginning of the project. - Answers -a. The requirements will be defined iteratively over
time.

Explanation:
Progressive elaboration involves defining requirements continuously throughout the
project and obtaining and adding more details and information to the plan as the details
become known.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
02 - Projects and Project Management

You notice that a project is behind schedule for four out of the five weeks. You perform
a trend analysis and predict that the project will also be behind this week. You are in the
process of submitting a change request to get the schedule back on track. What
process group are you in?

a. Initiating
b. Planning
c. Monitoring and Controlling
d. Closing - Answers -c. Monitoring and Controlling

Escuela, estudio y materia

Institución
CAPM
Grado
CAPM

Información del documento

Subido en
22 de febrero de 2026
Número de páginas
137
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$26.49
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF


Documento también disponible en un lote

Thumbnail
Package deal
CAPM BUNDLED EXAMS
-
13 2026
$ 185.87 Más información

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Greaterheights Birkbeck, University of London
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1143
Miembro desde
4 año
Número de seguidores
882
Documentos
19566
Última venta
2 días hace

4.0

221 reseñas

5
121
4
43
3
24
2
11
1
22

Documentos populares

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes