1. A project monitoring system involves all of the following except:
A. Determining what date to collect
B. Determining how, when, and who will collect the data
C. Adjusting the data
D. Analysis of the data
E. Reporting current progress Answer: C
2. Adequate project controls have the advantage(s) of:
A. Holding people accountable
B. Prevents small problems from getting large
C. Keeping focus
D. Both A and B are correct
E. A, B, and C are all correct Answer: E
3. A typical project progress report would contain all of the following sections
except:
A. Progress since last report
B. Problems and issues since last report
C. Current status of project
D. Corrective action planned
E. All of these are typical sections Answer: E
4. The first step in the project control process of the measurement and
evaluation of project performance is to
1
APPHIA - Crafted with Care and Precision for Academic Excellence.
,A. Set a baseline plan
B. Determine the project objectives
C. Determine the project deliverables
D. Analyze the project budget
E. Review the project priority matrix Answer: A
5. The second step in the project control process of the measurement and
evaluation of project performance is to:
A. Review the baseline plan with top management
B. Analyze inputs to control system
C. Compare plan against actual
D. Measure progress and performance
E. Review spending with team members Answer: D
6. The third step in the project control process of the measurement and
evaluation of project performance is to:
A. Review the baseline plan with top management
B. Analyze inputs to the control system
C. Compare the plan against actual performance
D. Measure both progress and performance
E. Review spending with team members Answer: C
7. The last step in the project control process of the measurement and
evaluation of project performance is to:
A. Take appropriate action
2
APPHIA - Crafted with Care and Precision for Academic Excellence.
,B. Prepare a report to top management
C. Follow up on corrective action
D. Measure progress and performance
E. Review spending with team members Answer: A
8. In monitoring project time (schedule) performance actual performance
should be compared to:
A. Budgets for the current year
B. Top management's targets
C. Project network schedule derived from the WBS/OBS
D. Progress on similar past projects
E. Previous status reports Answer: C
9. A typical tool used to communicate project status is a:
A. Project network diagram
B. Gantt Chart
C. A PERT chart
D. Both A and B are correct
E. A, B, and C are all correct Answer: B
10. A tool used to monitor past project schedule performance, current
performance, and to estimate future schedule trends is a simple line chart
known as a:
A. Project schedule control chart
B. Gantt chart
3
APPHIA - Crafted with Care and Precision for Academic Excellence.
, C. PERT chart
D. Network diagram
E. Milestone chart Answer: A
11. n Earned Value System used to monitor project progress includes
comparison of
A. Actual costs versus budget
B. Schedule progress versus plan
C. Quality progress versus plan
D. Both A and B are correct
E. A, B, and C are all correct Answer: D
12. he earned value of a project is the:
A. Project cost to date adjusted for project scope changes
B. Total project cost to date
C. Cost incurred minus the planned cost
D. Percent of the original budget that has been earned by actual work
E. None of these are correct Answer: D
13. The cost variance for a project is calculated by: A. EV-AC
B. AC-SV
C. PV-EV
D. CU-EV
E. EU-PV Answer: A
4
APPHIA - Crafted with Care and Precision for Academic Excellence.
A. Determining what date to collect
B. Determining how, when, and who will collect the data
C. Adjusting the data
D. Analysis of the data
E. Reporting current progress Answer: C
2. Adequate project controls have the advantage(s) of:
A. Holding people accountable
B. Prevents small problems from getting large
C. Keeping focus
D. Both A and B are correct
E. A, B, and C are all correct Answer: E
3. A typical project progress report would contain all of the following sections
except:
A. Progress since last report
B. Problems and issues since last report
C. Current status of project
D. Corrective action planned
E. All of these are typical sections Answer: E
4. The first step in the project control process of the measurement and
evaluation of project performance is to
1
APPHIA - Crafted with Care and Precision for Academic Excellence.
,A. Set a baseline plan
B. Determine the project objectives
C. Determine the project deliverables
D. Analyze the project budget
E. Review the project priority matrix Answer: A
5. The second step in the project control process of the measurement and
evaluation of project performance is to:
A. Review the baseline plan with top management
B. Analyze inputs to control system
C. Compare plan against actual
D. Measure progress and performance
E. Review spending with team members Answer: D
6. The third step in the project control process of the measurement and
evaluation of project performance is to:
A. Review the baseline plan with top management
B. Analyze inputs to the control system
C. Compare the plan against actual performance
D. Measure both progress and performance
E. Review spending with team members Answer: C
7. The last step in the project control process of the measurement and
evaluation of project performance is to:
A. Take appropriate action
2
APPHIA - Crafted with Care and Precision for Academic Excellence.
,B. Prepare a report to top management
C. Follow up on corrective action
D. Measure progress and performance
E. Review spending with team members Answer: A
8. In monitoring project time (schedule) performance actual performance
should be compared to:
A. Budgets for the current year
B. Top management's targets
C. Project network schedule derived from the WBS/OBS
D. Progress on similar past projects
E. Previous status reports Answer: C
9. A typical tool used to communicate project status is a:
A. Project network diagram
B. Gantt Chart
C. A PERT chart
D. Both A and B are correct
E. A, B, and C are all correct Answer: B
10. A tool used to monitor past project schedule performance, current
performance, and to estimate future schedule trends is a simple line chart
known as a:
A. Project schedule control chart
B. Gantt chart
3
APPHIA - Crafted with Care and Precision for Academic Excellence.
, C. PERT chart
D. Network diagram
E. Milestone chart Answer: A
11. n Earned Value System used to monitor project progress includes
comparison of
A. Actual costs versus budget
B. Schedule progress versus plan
C. Quality progress versus plan
D. Both A and B are correct
E. A, B, and C are all correct Answer: D
12. he earned value of a project is the:
A. Project cost to date adjusted for project scope changes
B. Total project cost to date
C. Cost incurred minus the planned cost
D. Percent of the original budget that has been earned by actual work
E. None of these are correct Answer: D
13. The cost variance for a project is calculated by: A. EV-AC
B. AC-SV
C. PV-EV
D. CU-EV
E. EU-PV Answer: A