FDOT Asphalt Paving Level 2 Exam
Preparation||Verified Exam!!! Newest With Complete
Questions And Correct Detailed Answers||Newest
Exam!!
Which Document is used to authorize payment from
original contingency Amount? - Answer-Work Order
Friction Course (FC-12.5) Straight edge Deficiency: A
straightedge deficiency was left in place at no pay.
Calculate the equivalent tonnage at no pay. ( pay to
appropriate accuracy) Gmm= 2.417, thickness =1.5
inches, road width =12 feet, length of deficiency = 5 ft.
(this occurred 25 feet from the bridge deck) - Answer-8.4
Tons
Overruns or Underruns must be explained when? -
Answer-A pay item overruns or underruns $10,000 or
more.
Prices are adjusted on each progress estimate to reflect
increases or decreases in the price of fuel for contracts
with original Contract Time: - Answer-In excess of 120
calendar days.
, 2|Page
Which of the following is an authorized way to modify the
contract, once it has been executed? - Answer-Work
Orders and Supplimental Agreements
Of the Contract Documents listed below which one would
govern? - Answer-Special Provisions
On multi FIN project numbers under one contract, the
Asphalt is reported on the certification, by the
CONTRACTOR, under what Project FIN Number? -
Answer-The Contractor shows the Asphalt on the lead FIN
project number
A roadway is being constructed and has a Subsoil
Excavation Quantity of 835 CY, a Regular Excavation
Quantity of 250 CY and an embankment Quantity of 1040
CY. Based upon this information, the Final Quantity to be
paid for embankment will be? - Answer-1875 CY
Why is it important to run a progress estimate soon after
Final Acceptance? - Answer-So the estimate can be paid
through EED quickly to prevent interest.