Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 2 fuera de 5 páginas
Examen

CQM-C EXAM QUESTIONS AND ANSWERS GRADED A+

Document preview thumbnail
Vista previa 2 fuera de 5 páginas

CQM-C EXAM QUESTIONS AND ANSWERS GRADED A+CQM-C EXAM QUESTIONS AND ANSWERS GRADED A+

Vista previa del contenido

CQM Course Questions



A cumulative list of job deficiencies/rework items can be found in: - ANS>>Quality
Control Report

Contractor benefits of CQM - ANS>>Increased profit and production, better
communications, planning, improved organizational skills, and outstanding performance
evaluations to obtain future contracts.

contractor quality control function - ANS>>To assure that the completed project meets
all quality requirements of the contract.

Purpose of CQM - ANS>>The government's efforts, separate from, but in coordination
and cooperation with the contractor, assure that the quality set by the plans and
specifications is achieved.

Two factors cause construction industry to become highly specialized - ANS>>changing
markets and increased tech and regulations

Factor that will influence both government and construction industry in the future -
ANS>>New government regulations, greater influence from consumer, improvement in
QC and QA requirements, construction-oriented management info systems, formal
partnering involving stakeholders, more reliance on design-build, more considerate for
live cycle requirements and increased based incentives

A definable feature of work: - ANS>>Can consist of a combination of multiple
specification sections depending upon the nature of the work

Actual construction on the jobsite begins: - ANS>>After an interim or final QC is
accepted

All submittals for government approval must be provided by the _________________ in
time to allow for the review, approval, procurement, delivery, and performance of
preparatory phase for an item before it is needed for construction. - ANS>>Contractor to
the Government

An effective contractor quality control program will - ANS>>Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead
costs, and greater profits

, Characteristics that describe a definable feature of work include: - ANS>>Cross-
referenced listings to the contractor's construction schedule that may have more than
one definable feature under a section of the specifications

Construction Quality Management is the performance of tasks, which ensure that
construction is performed: - ANS>>According to plans and specifications, on time,
within a defined budget and a safe work environment

Contractor testing procedures: - ANS>>are outlined in the Quality Control Plan as
defined by section 0145N/01451A and addressed at the Coordination and Mutal
Understanding Meeting (Navy).

Control is - ANS>>A continual system of planned future activities (its preventative)

Design-Build contracts require - ANS>>The QC Manager to be in place and take an
active role in the review and coordination of the design.

During the punch-out inspection of a project: - ANS>>The contractor prepares a punch
list and makes corrections

ENG Form 4288-R, the submittal register - ANS>>identifies this submittals requiring
government approval

Ground for withholding payment include the contractor's failure to - ANS>>Perform in
accordance with the terms of the contract, provide an acceptable Quality Control Plan
giving assurance of intent and ability to comply with quality standards, and build to the
quality standards established by the contract

If initial review of the quality control plan shows it to be unacceptable - ANS>>The
contractor makes changes before acceptance

If the contractor does not provide an adequate superintendent, the contract allows the
contracting officer to - ANS>>Require the contractor to assume personal supervision of
the work

If there is a disagreement whether the contractor's work complies with the contract: -
ANS>>The government makes the final determination

In a design build contract, if the contractor has a question about the design, what is the
process to get an answer? - ANS>>Contractor submits a Design Verification
Clarification Request (DVCR) to the contractor's design team

Inspection is: - ANS>>The process by which ongoing and completed work is examined

It is the responsibility of Quality Assurance Personnel to - ANS>>Periodically verify that
the contractor's system of control is working effectively

Información del documento

Subido en
28 de enero de 2026
Número de páginas
5
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
1
Seguidores
1
Artículos
170
Última venta
9 meses hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes