UPDATE!!!!2025/2026|GUARANTEED PASS|GRADED
1 meter = 3.28 ft = ____ inches - ANSWER 39.37 inches
1 sq ft = ____ sq in - ANSWER 144 sq in
1 sq yd = ___ sq ft - ANSWER 9 sq ft
1 acre = ______ square feet - ANSWER 43,560 square feet
1 sq mile = ____ acres - ANSWER 640 acres
1 cu ft = ____ cu in - ANSWER 1728 cu in
1 cu yd = ___ cu ft - ANSWER 27 cu ft
1 cu ft of sand ~= _ _ lbs - ANSWER 100 lbs
1 roofing square = ___ sq ft - ANSWER 100 sq ft
Area of a Rectangle = - ANSWER base x height
1
, are of a square = - ANSWER s * s = s^2
The area of a triangle equals - ANSWER half the product of a base and the height to
that base (A=1/2bh)
area of a trapezoid equals - ANSWER Half the product of the height and the sum of the
bases ((a+b)/2)*h
Circumference = - ANSWER pi x diameter = 2*pi*r
area of a circle equals - ANSWER 2(pi) * r^2
Volume of a cube equals - ANSWER V = s*s*s
Volume of a rectangle equals - ANSWER v=b*h*d
Volume of a cylinder equals - ANSWER (pi) * (r^2) * h
Special Detailed requirements on use and occupancy:
Every required exit doorway must be large enough to allow the installation of a door with
minimum dimensions of __(width) x __(height). Once installed exit doors must be capable of
opening so that the clear width of the exit is at least ____ inches. - ANSWER 3 feet 0
inches(width) , 6 feet 8 inches(height) ; 32 inches
A local building department may __________ an applicant for a ________ to submit plans
and specifications for _________. Once approved, one set of plans and specifications must
be _______ on file by the department for up to _____ after completion of the project. The
department must also, upon approval, return a set of the plans and specifications to the
applicant. This second set must be kept at the jobsite during the entire project. Every permit
issued will become invalid if the work authorized was not begun within ________ days after
2
1 meter = 3.28 ft = ____ inches - ANSWER 39.37 inches
1 sq ft = ____ sq in - ANSWER 144 sq in
1 sq yd = ___ sq ft - ANSWER 9 sq ft
1 acre = ______ square feet - ANSWER 43,560 square feet
1 sq mile = ____ acres - ANSWER 640 acres
1 cu ft = ____ cu in - ANSWER 1728 cu in
1 cu yd = ___ cu ft - ANSWER 27 cu ft
1 cu ft of sand ~= _ _ lbs - ANSWER 100 lbs
1 roofing square = ___ sq ft - ANSWER 100 sq ft
Area of a Rectangle = - ANSWER base x height
1
, are of a square = - ANSWER s * s = s^2
The area of a triangle equals - ANSWER half the product of a base and the height to
that base (A=1/2bh)
area of a trapezoid equals - ANSWER Half the product of the height and the sum of the
bases ((a+b)/2)*h
Circumference = - ANSWER pi x diameter = 2*pi*r
area of a circle equals - ANSWER 2(pi) * r^2
Volume of a cube equals - ANSWER V = s*s*s
Volume of a rectangle equals - ANSWER v=b*h*d
Volume of a cylinder equals - ANSWER (pi) * (r^2) * h
Special Detailed requirements on use and occupancy:
Every required exit doorway must be large enough to allow the installation of a door with
minimum dimensions of __(width) x __(height). Once installed exit doors must be capable of
opening so that the clear width of the exit is at least ____ inches. - ANSWER 3 feet 0
inches(width) , 6 feet 8 inches(height) ; 32 inches
A local building department may __________ an applicant for a ________ to submit plans
and specifications for _________. Once approved, one set of plans and specifications must
be _______ on file by the department for up to _____ after completion of the project. The
department must also, upon approval, return a set of the plans and specifications to the
applicant. This second set must be kept at the jobsite during the entire project. Every permit
issued will become invalid if the work authorized was not begun within ________ days after
2