⩥ The ______________ is responsible for approving the special
inspection program. Answer: The building official
⩥ Who does the special inspector notify first if there is a non-
conforming item? Answer: The inspection supervisor
⩥ How often does the special inspector submit reports to the building
official? Answer: As determined by the building official
⩥ Who establishes the special inspection program? Answer: The
building department
⩥ Who submits the statement of responsibility? Answer: The contractor
⩥ Who produces the statement of responsibility? Answer: The contractor
⩥ A preconstruction meeting is: Answer: Initiated by the general
contractor
EXAM PAPER 2026 FULL QUESTIONS AND
VERIFIED ANSWERS GRADED A+
⩥ The ______________ is responsible for approving the special
inspection program. Answer: The building official
⩥ Who does the special inspector notify first if there is a non-
conforming item? Answer: The inspection supervisor
⩥ How often does the special inspector submit reports to the building
official? Answer: As determined by the building official
⩥ Who establishes the special inspection program? Answer: The
building department
⩥ Who submits the statement of responsibility? Answer: The contractor
⩥ Who produces the statement of responsibility? Answer: The contractor
⩥ A preconstruction meeting is: Answer: Initiated by the general
contractor